How to apply for a building permit in unincorporated Chickasaw County, Mississippi. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Chickasaw County Board of Supervisors

Street address
1 Pinson Square, Houston, MS 38851
Coverage
All properties in unincorporated areas of Chickasaw County.
§ 02

When a permit is required

Permit triggers and exempt work for Chickasaw County

Required for any construction, renovation, structural repair, or land development in unincorporated areas.

Farm buildings and farm structures (with limitations; floodplain regulations override agricultural exemptions)
Structures exempt under Mississippi Code § 17-2-7 (subject to Flood Disaster Protection Act of 1973 override)
  • Exempt Farm buildings and farm structures (with limitations; floodplain regulations override agricultural exemptions)
  • Exempt Structures exempt under Mississippi Code § 17-2-7 (subject to Flood Disaster Protection Act of 1973 override)

Note: Agricultural exemptions do not apply to floodplain management ordinances required for National Flood Insurance Program eligibility. Flood Disaster Protection Act of 1973 requirements override exemptions in designated floodplain areas.

Required documents
  • Permit application form
  • Building plans
  • Project specifications
  • Contractor information
Building code
Chickasaw County may adopt any of the latest three editions of the International Building Code (IBC) and International Residential Code (IRC). Contact county for current adoption status and code version.
Permit validity
Contact county office for permit expiration requirements
Owner-builder
Contact county for owner-builder requirements
Contractor requirements
Contractor information required by Mississippi law. Check MSBOC licensing requirements if project exceeds state thresholds.
§ 03

Application process

Typical processing: Contact county office for processing timeline

  1. 01
    Contact Chickasaw County Board of Supervisors or County Clerk's office at 662-456-3941
  2. 02
    Obtain permit application form from county office
  3. 03
    Provide contractor information as required by Mississippi law
  4. 04
    Submit application with building plans and project specifications
  5. 05
    Pay applicable permit fee
  6. 06
    Receive permit or notice of denial

Typical processing time: Contact county office for processing timeline

§ 04

Fee schedule

Chickasaw County building permit fees

Fee type
Amount
01
Permit fee formula
Not published online; contact county office for current fee schedule
§ 05

Required inspections

Scheduling and sequence

Inspection hours
Monday–Friday, standard business hours

Typical sequence: Mississippi law requires permits for all construction, which implies inspection stages. Contact county building department for specific inspection timeline and requirements.

§ 06

Frequently asked

Common questions about unincorporated Chickasaw County permits

01 Do I need a building permit in unincorporated Chickasaw County, MS?
Required for any construction, renovation, structural repair, or land development in unincorporated areas.
02 How much does a building permit cost in unincorporated Chickasaw County, MS?
Building permit fees in unincorporated Chickasaw County, MS are set by the local building department and vary by project type and valuation. Fees are calculated as: Not published online; contact county office for current fee schedule.
03 How do I apply for a building permit in unincorporated Chickasaw County, MS?
To apply for a building permit in unincorporated Chickasaw County, MS, follow these steps: 1. Contact Chickasaw County Board of Supervisors or County Clerk's office at 662-456-3941 2. Obtain permit application form from county office 3. Provide contractor information as required by Mississippi law 4. Submit application with building plans and project specifications 5. Pay applicable permit fee 6. Receive permit or notice of denial
04 How long does it take to get a building permit in unincorporated Chickasaw County, MS?
Building permit processing times in unincorporated Chickasaw County, MS typically run Contact county office for processing timeline. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in unincorporated Chickasaw County, MS?
Not all construction work requires a permit in unincorporated Chickasaw County, MS. The following work is generally exempt: Farm buildings and farm structures (with limitations; floodplain regulations override agricultural exemptions); Structures exempt under Mississippi Code § 17-2-7 (subject to Flood Disaster Protection Act of 1973 override). Note: Agricultural exemptions do not apply to floodplain management ordinances required for National Flood Insurance Program eligibility. Flood Disaster Protection Act of 1973 requirements override exemptions in designated floodplain areas. When in doubt, confirm with the local building department before starting work.