How to apply for a building permit in unincorporated Bolivar County, Mississippi. Permit authority, application steps, fees, and inspection requirements.

Avg processing
7-10 working days for county review
Last verified
April 2026
On this page 5
§ 01

Permit authority

County Administrator's Office / Planning Division

Street address
Bolivar County Courthouse, Rosedale, MS
Coverage
All unincorporated areas outside all municipalities within Bolivar County.
§ 02

When a permit is required

Permit triggers and exempt work for Bolivar County

Almost any work requiring land disturbance, construction, or structural modification requires a permit in unincorporated areas.

Note: Agricultural exemptions may apply; verify with county Planning Division. Properties in FEMA flood zones require floodplain development permits regardless of work type.

Required documents
  • Completed permit application
  • Construction plans
  • Site surveys
Building code
Bolivar County adopts the International Building Code (IBC) or International Residential Code (IRC); typically 2012, 2015, 2018, or 2021 editions
Contractor requirements
Contractors must comply with Mississippi State Board of Contractors licensing requirements.
§ 03

Application process

Typical processing: 7-10 working days for county review

  1. 01
    Contact Bolivar County Planning Division at 662-846-5877 to determine zoning requirements and submittal requirements
  2. 02
    Prepare construction plans and site surveys per county standards
  3. 03
    Submit application and plans to the County Administrator's Office
  4. 04
    County reviews application for code compliance (typically within 7-10 working days)
  5. 05
    Upon approval, permit is issued
  6. 06
    Schedule inspections with county inspector as work progresses

Typical processing time: 7-10 working days for county review

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • County Planning Division (phone)

Typical sequence: Required inspections typically include: foundation/footing, framing, electrical, plumbing, mechanical, and final occupancy.

§ 05

Frequently asked

Common questions about unincorporated Bolivar County permits

01 Do I need a building permit in unincorporated Bolivar County, MS?
Almost any work requiring land disturbance, construction, or structural modification requires a permit in unincorporated areas.
02 How do I apply for a building permit in unincorporated Bolivar County, MS?
To apply for a building permit in unincorporated Bolivar County, MS, follow these steps: 1. Contact Bolivar County Planning Division at 662-846-5877 to determine zoning requirements and submittal requirements 2. Prepare construction plans and site surveys per county standards 3. Submit application and plans to the County Administrator's Office 4. County reviews application for code compliance (typically within 7-10 working days) 5. Upon approval, permit is issued 6. Schedule inspections with county inspector as work progresses
03 How long does it take to get a building permit in unincorporated Bolivar County, MS?
Building permit processing times in unincorporated Bolivar County, MS typically run 7-10 working days for county review. Timelines can vary based on project complexity and current department workload.
04 How do I schedule a building inspection in unincorporated Bolivar County, MS?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in unincorporated Bolivar County, MS via: County Planning Division.
last verified April 2026 entry id permits/mississippi/bolivar/unincorporated

Educational reference. Permit rules and fees change — confirm current requirements directly with County Administrator's Office / Planning Division before applying. Jaspector is not legal advice.