jaspector
City building permits

May Township

How to apply for a building permit in May Township, Minnesota. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 5
§ 01

Permit authority

Applications and Permits, Town of May

Street address
May Town Hall, 14960 62nd Street N, Stillwater, MN 55082
Coverage
Township permit authority for unincorporated May Township parcels
Online portal
Permit portal
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for May Township

The township publishes separate building, land use, electrical, grading, wetland, and septic permit pages

Required documents
  • Permit application, plans, site information, and permit-specific supplements
Building code
Minnesota State Building Code as locally administered
Permit validity
Verify on current township forms
Contractor requirements
Minnesota licensing rules apply
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Confirm the parcel is in unincorporated May Township.
  2. 02
    Use the township Applications and Permits page to select the correct building, land-use, grading, wetland, electrical, or septic form.
  3. 03
    Submit the building permit materials and plans to the township's designated contact.
  4. 04
    Pay fees after review and wait for issuance before construction.
  5. 05
    Schedule inspections with the designated building official.

Source: Applications and Permits, Town of May ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • Through the township-designated building official (contact)

Typical sequence: Project-dependent building and trade inspections followed by final

Reinspection required after corrections

§ 05

Frequently asked

Common questions about May Township permits

01 Do I need a building permit in May Township, MN?
The township publishes separate building, land use, electrical, grading, wetland, and septic permit pages
02 How do I apply for a building permit in May Township, MN?
To apply for a building permit in May Township, MN, follow these steps: 1. Confirm the parcel is in unincorporated May Township. 2. Use the township Applications and Permits page to select the correct building, land-use, grading, wetland, electrical, or septic form. 3. Submit the building permit materials and plans to the township's designated contact. 4. Pay fees after review and wait for issuance before construction. 5. Schedule inspections with the designated building official.
03 How do I schedule a building inspection in May Township, MN?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in May Township, MN via: Through the township-designated building official.
last verified April 2026 source Applications and Permits, Town of May ↗ entry id permits/minnesota/washington-mn/may-township

Educational reference. Permit rules and fees change — confirm current requirements directly with Applications and Permits, Town of May before applying. Jaspector is not legal advice.