How to apply for a building permit in City of Ely, Minnesota. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 5
§ 01

Permit authority

City of Ely Building Department

Street address
City Hall, 209 E Chapman Street, Ely, MN 55731
Coverage
DLI lists ELY as having adopted the Minnesota State Building Code with local enforcement.
§ 02

When a permit is required

Permit triggers and exempt work for Ely

Permits are required for most building projects within the city.

Note: No city-specific exempt-work list was located in the reviewed sources. Confirm with the Building Department before relying on any exemption.

Required documents
  • Building permit application
  • Construction documents
  • Site plan
  • Manufacturer instructions or licensed design professional plans as required by the Building Official
Building code
Yes. DLI directory lists ELY as adopted and locally enforced.
Contractor requirements
Minnesota state specialty licensing applies. Confirm any local requirements with the Building Department.
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Submit the permit application with construction documents and site plan as required by the submittal-documents handout.
  2. 02
    Provide any additional information requested by the Building Official.
  3. 03
    Wait for permit issuance before starting work.
  4. 04
    Schedule inspections by phone at least 24 hours in advance.
  5. 05
    Request final inspection and certificate of occupancy when work is complete.

Source: City of Ely Building Department ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • Call Building Department — (218) 504-5142 (phone)
Scheduling deadline
At least 24 hours in advance; requests left on voicemail are not confirmed until staff contact occurs
Inspection hours
Inspections normally 8:00 AM to 4:30 PM, Monday-Friday

Typical sequence: Typical sequence: footing, foundation, rough heating, rough plumbing, rough electrical, frame, insulation, septic as applicable, finals, and final inspection.

Source: City of Ely Building Department ↗

§ 05

Frequently asked

Common questions about Ely permits

01 Do I need a building permit in Ely, MN?
Permits are required for most building projects within the city.
02 How do I apply for a building permit in Ely, MN?
To apply for a building permit in Ely, MN, follow these steps: 1. Submit the permit application with construction documents and site plan as required by the submittal-documents handout. 2. Provide any additional information requested by the Building Official. 3. Wait for permit issuance before starting work. 4. Schedule inspections by phone at least 24 hours in advance. 5. Request final inspection and certificate of occupancy when work is complete.
03 How do I schedule a building inspection in Ely, MN?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Ely, MN via: Call Building Department — (218) 504-5142. At least 24 hours in advance; requests left on voicemail are not confirmed until staff contact occurs.
last verified April 2026 source City of Ely Building Department ↗ entry id permits/minnesota/st-louis/ely

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Ely Building Department before applying. Jaspector is not legal advice.