§ 01

Permit authority

Township Cooperative Planning Association (TCPA) outside Stewartville city limits

Street address
Stewartville Fire Hall, 417 1/2 South Main, Stewartville, MN 55976
Coverage
County routing sends High Forest Township projects outside Stewartville city limits to TCPA; Stewartville parcels route to the city/county split used by Stewartville.
Online portal
iWorQ portal used by TCPA/CMS
iWorQ portal used by TCPA/CMS
§ 02

When a permit is required

Permit triggers and exempt work for High Forest Township

TCPA permit routing applies to township building and zoning work outside city limits.

No township-specific exempt-work list located.
  • Exempt No township-specific exempt-work list located.
Required documents
  • TCPA form set
  • project-specific plans.
Building code
Minnesota State Building Code plus township controls.
Owner-builder
Self-waiver for owners signing permit applications.
Contractor requirements
Minnesota licensing rules apply.
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Confirm the project is outside Stewartville city limits.
  2. 02
    File online or on paper through TCPA.
  3. 03
    Include the required forms, plans, and waiver if owner-built.
  4. 04
    Pay the applicable fee.
  5. 05
    Wait for issuance through the TCPA/CMS review workflow.
  6. 06
    Schedule inspections through CMS.

Source: Township Cooperative Planning Association (TCPA) outside Stewartville city limits ↗

§ 04

Fee schedule

High Forest Township building permit fees

Fee type
Amount
01
Minimum permit fee
$125 maintenance permit; $137 non-maintenance flat-fee permit.
02
Permit fee formula
Valued and flat-fee categories.

Prepaid paper flat-fee permits or online card/ACH payment.

§ 05

Required inspections

Scheduling and sequence

How to schedule

Typical sequence: Project-dependent.

§ 06

Frequently asked

Common questions about High Forest Township permits

01 Do I need a building permit in High Forest Township, MN?
TCPA permit routing applies to township building and zoning work outside city limits.
02 How much does a building permit cost in High Forest Township, MN?
Building permit fees in High Forest Township, MN are set by the local building department and vary by project type and valuation. The minimum permit fee is $125 maintenance permit; $137 non-maintenance flat-fee permit.. Fees are calculated as: Valued and flat-fee categories..
03 How do I apply for a building permit in High Forest Township, MN?
To apply for a building permit in High Forest Township, MN, follow these steps: 1. Confirm the project is outside Stewartville city limits. 2. File online or on paper through TCPA. 3. Include the required forms, plans, and waiver if owner-built. 4. Pay the applicable fee. 5. Wait for issuance through the TCPA/CMS review workflow. 6. Schedule inspections through CMS.
04 What work is exempt from building permits in High Forest Township, MN?
Not all construction work requires a permit in High Forest Township, MN. The following work is generally exempt: No township-specific exempt-work list located.. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in High Forest Township, MN?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in High Forest Township, MN via: Online scheduling.
last verified April 2026 source Township Cooperative Planning Association (TCPA) outside Stewartville city limits ↗ entry id permits/minnesota/olmsted/high-forest-township