§ MN Anoka County
City building permits

Andover

How to apply for a building permit in Andover, Minnesota. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Building Department

Street address
Andover City Hall, 1685 Crosstown Boulevard NW, Andover, MN 55304
Coverage
City building department administers permits and inspections inside city limits
Online portal
Baseline
Baseline
§ 02

When a permit is required

Permit triggers and exempt work for Andover

New construction, remodeling, additions, alterations, basement finishes, decks, porches, irrigation systems, and similar regulated work

Normal maintenance and repair such as concrete surface repair
Replacement of deck boards
Small sections of siding or shingles
Window sash repair or replacement
Glass repair
  • Exempt Normal maintenance and repair such as concrete surface repair
  • Exempt Replacement of deck boards
  • Exempt Small sections of siding or shingles
  • Exempt Window sash repair or replacement
  • Exempt Glass repair
Required documents
  • When a permit is required: New construction, remodeling, additions, alterations, basement finishes, decks, porches, irrigation systems, and similar regulated work
  • Required documents: Application, plans, and other construction documents; Andover says to bring two copies when scaled plans are required
  • Permit validity/expiration: State-code baseline unless extended; verify on issued permit
  • Owner-builder rules if available: Permits are required whether work is done by a contractor or homeowner
  • Contractor license requirements: State licensed contractors required where mandated by state law; city also licenses mechanical contractors
  • Building code adopted: Minnesota State Building Code with local administration
Building code
Minnesota State Building Code with local administration
Permit validity
State-code baseline unless extended; verify on issued permit
Owner-builder
Permits are required whether work is done by a contractor or homeowner
Contractor requirements
State licensed contractors required where mandated by state law; city also licenses mechanical contractors
§ 03

Application process

Typical processing: Residential projects typically reviewed immediately or within 1 to 2 days; commercial permits typically 5 to 10 days

  1. 01
    Determine whether the project can use Andover's online Baseline portal or requires PDF submittal.
  2. 02
    Submit the online application, or submit the fillable PDF by email, mail, or at City Hall with required plans and supporting documents.
  3. 03
    Building staff reviews the submission and may request additional documents.
  4. 04
    Pay permit fees after approval.
  5. 05
    Permit is issued and inspections are scheduled with the building department.

Typical processing time: Residential projects typically reviewed immediately or within 1 to 2 days; commercial permits typically 5 to 10 days

Source: Building Department ↗

§ 04

Fee schedule

Andover building permit fees

Fee type
Amount
01
Minimum permit fee
Check current fee schedule; city notes valuation-based building fees
02
Permit fee formula
Valuation-based for residential and commercial building permits; state valuation data used
03
Reinspection fee
Additional review and related charges appear in the fee schedule

Online and in-person payments accepted; prior system users were migrated to 2026 Baseline payment links

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

Typical sequence: Project-dependent; footing, framing, trade rough-ins, insulation, and final for larger jobs

§ 06

Frequently asked

Common questions about Andover permits

01 Do I need a building permit in Andover, MN?
New construction, remodeling, additions, alterations, basement finishes, decks, porches, irrigation systems, and similar regulated work
02 How much does a building permit cost in Andover, MN?
Building permit fees in Andover, MN are set by the local building department and vary by project type and valuation. The minimum permit fee is Check current fee schedule; city notes valuation-based building fees. Fees are calculated as: Valuation-based for residential and commercial building permits; state valuation data used.
03 How do I apply for a building permit in Andover, MN?
To apply for a building permit in Andover, MN, follow these steps: 1. Determine whether the project can use Andover's online Baseline portal or requires PDF submittal. 2. Submit the online application, or submit the fillable PDF by email, mail, or at City Hall with required plans and supporting documents. 3. Building staff reviews the submission and may request additional documents. 4. Pay permit fees after approval. 5. Permit is issued and inspections are scheduled with the building department.
04 How long does it take to get a building permit in Andover, MN?
Building permit processing times in Andover, MN typically run Residential projects typically reviewed immediately or within 1 to 2 days; commercial permits typically 5 to 10 days. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Andover, MN?
Not all construction work requires a permit in Andover, MN. The following work is generally exempt: Normal maintenance and repair such as concrete surface repair; Replacement of deck boards; Small sections of siding or shingles; Window sash repair or replacement; Glass repair. When in doubt, confirm with the local building department before starting work.
last verified April 2026 source Building Department ↗ entry id permits/minnesota/anoka/andover

Educational reference. Permit rules and fees change — confirm current requirements directly with Building Department before applying. Jaspector is not legal advice.