jaspector
City building permits

City of Lake City

How to apply for a building permit in City of Lake City, Michigan. Permit authority, application steps, fees, and inspection requirements.

Min. permit fee
Land Use Permit $40.00.
Last verified
April 2026
On this page 6
§ 01

Permit authority

City of Lake City Planning and Zoning, with building code enforcement by the Missaukee County Building Department

Street address
115 W John St, PO Box 1, Lake City, MI 49651
Coverage
Incorporated City of Lake City. The city zoning ordinance states that the building official is the Missaukee County Building Department official designated by the county board.
§ 02

When a permit is required

Permit triggers and exempt work for Lake City

Site development, zoning-sensitive uses, special land use, variance, and utility hookup work require city review. Construction work also routes through the county building department under the zoning ordinance.

Required documents
  • Site plan, application materials, and any outside permit approvals required by road, fire, health, soil erosion, or EGLE authorities.
Building code
The city zoning ordinance directs building code enforcement to the county building department and county building codes. The county application references the 2015 Michigan Building Code and 2015 Michigan Residential Code.
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Schedule a pre-application meeting with city staff.
  2. 02
    Submit site plan or zoning application and plans.
  3. 03
    City staff and zoning administrator review the proposal.
  4. 04
    Outside approvals may be required from fire, health, road jurisdiction, soil erosion, EGLE, and similar agencies.
  5. 05
    If approved, the zoning permit is issued.
  6. 06
    For code construction work, county building permit review still applies because the city ordinance assigns building code administration to the county building department.

Source: City of Lake City Planning and Zoning, with building code enforcement by the Missaukee County Building Department ↗

§ 04

Fee schedule

Lake City building permit fees

Fee type
Amount
01
Minimum permit fee
Land Use Permit $40.00.
02
Permit fee formula
Published fee table, not formula based, for zoning items and rentals. New water and sewer hookup is $3,000.00.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • City zoning page directs applicants to contact the city administrator; county inspections apply for actual building perm (online)

Typical sequence: Pre-application meeting, submit plan, staff review, outside agency approvals if required, planning commission review if needed, then zoning permit issuance.

§ 06

Frequently asked

Common questions about Lake City permits

01 Do I need a building permit in Lake City, MI?
Site development, zoning-sensitive uses, special land use, variance, and utility hookup work require city review. Construction work also routes through the county building department under the zoning ordinance.
02 How much does a building permit cost in Lake City, MI?
Building permit fees in Lake City, MI are set by the local building department and vary by project type and valuation. The minimum permit fee is Land Use Permit $40.00.. Fees are calculated as: Published fee table, not formula based, for zoning items and rentals. New water and sewer hookup is $3,000.00..
03 How do I apply for a building permit in Lake City, MI?
To apply for a building permit in Lake City, MI, follow these steps: 1. Schedule a pre-application meeting with city staff. 2. Submit site plan or zoning application and plans. 3. City staff and zoning administrator review the proposal. 4. Outside approvals may be required from fire, health, road jurisdiction, soil erosion, EGLE, and similar agencies. 5. If approved, the zoning permit is issued. 6. For code construction work, county building permit review still applies because the city ordinance assigns building code administration to the county building department.
04 How do I schedule a building inspection in Lake City, MI?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Lake City, MI via: City zoning page directs applicants to contact the city administrator; county inspections apply for actual building perm.

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Lake City Planning and Zoning, with building code enforcement by the Missaukee County Building Department before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Missaukee County.

Same county, different permit office. Click for that jurisdiction's full guide.