§ 01

Permit authority

Town of Centreville Department of Planning and Zoning

Street address
101 Lawyers Row, Centreville, MD 21617
Coverage
Administers zoning ordinance and building permit process within town limits. The town enforces the Maryland State Building Code (2021 IBC/IRC, 2020 NEC).
Online portal
Town of Centreville Forms Page
Paper-based
§ 02

When a permit is required

Permit triggers and exempt work for Centreville

A building permit is required within the Town of Centreville for construction, reconstruction, enlargement, alteration, or demolition of any building or structure.

Note: Not specified in available public sources. The Maryland State Building Code IRC section on exempt work generally applies (e.g., certain ordinary repairs); verify with Town Hall for specific exemptions applicable within Centreville.

Required documents
  • Building permit application
  • Site plan
  • Building plans
  • Contractor license documentation
Building code
Maryland State Building Code (2021 IBC, 2021 IRC, 2020 NEC and Maryland amendments) as enforced by the town.
Permit validity
Not confirmed from public sources; contact Town Hall.
Owner-builder
Not confirmed from public sources; contact Town Hall.
Contractor requirements
Maryland Home Builders license (new construction) and MHIC license (renovations/repairs) apply as statewide requirements. The town may have additional local contractor registration requirements; confirm with Town Hall.
§ 03

Application process

Typical processing: Not published; contact Town Hall at (410) 758-1180 for current estimates.

  1. 01
    Confirm the property is within Centreville town limits.
  2. 02
    Contact Town Hall at (410) 758-1180 to confirm permit type needed and current submittal requirements.
  3. 03
    Obtain relevant application forms from https://www.townofcentreville.org/forms or in person at Town Hall.
  4. 04
    Prepare site plan, building plans, contractor information, and any zoning compliance documentation as required.
  5. 05
    Submit application in person at Town Hall (101 Lawyers Row, Centreville, MD 21617).
  6. 06
    Await review and approval; the town coordinates with state and county agencies as needed.
  7. 07
    Schedule inspections through MDIA (Middle Department Inspection Agency) at 410-822-8300.
  8. 08
    Upon completion of all inspections, obtain Certificate of Occupancy from the town.

Typical processing time: Not published; contact Town Hall at (410) 758-1180 for current estimates.

Source: Town of Centreville Department of Planning and Zoning ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • MDIA at (410) 822-8300 (phone)
Scheduling deadline
Call at least 24 hours in advance.

Typical sequence: Follows Maryland State Building Code inspection requirements (footing, foundation, framing, insulation, final for residential work).

§ 05

Frequently asked

Common questions about Centreville permits

01 Do I need a building permit in Centreville, MD?
A building permit is required within the Town of Centreville for construction, reconstruction, enlargement, alteration, or demolition of any building or structure.
02 How do I apply for a building permit in Centreville, MD?
To apply for a building permit in Centreville, MD, follow these steps: 1. Confirm the property is within Centreville town limits. 2. Contact Town Hall at (410) 758-1180 to confirm permit type needed and current submittal requirements. 3. Obtain relevant application forms from https://www.townofcentreville.org/forms or in person at Town Hall. 4. Prepare site plan, building plans, contractor information, and any zoning compliance documentation as required. 5. Submit application in person at Town Hall (101 Lawyers Row, Centreville, MD 21617). 6. Await review and approval; the town coordinates with state and county agencies as needed. 7. Schedule inspections through MDIA (Middle Department Inspection Agency) at 410-822-8300. 8. Upon completion of all inspections, obtain Certificate of Occupancy from the town.
03 How long does it take to get a building permit in Centreville, MD?
Building permit processing times in Centreville, MD typically run Not published; contact Town Hall at (410) 758-1180 for current estimates.. Timelines can vary based on project complexity and current department workload.
04 How do I schedule a building inspection in Centreville, MD?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Centreville, MD via: MDIA at (410) 822-8300. Call at least 24 hours in advance..
last verified April 2026 source Town of Centreville Department of Planning and Zoning ↗ entry id permits/maryland/queen-annes/centreville

Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Centreville Department of Planning and Zoning before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Queen Anne's County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Queen Anne's County jurisdictions →