Town of Hillsboro

How to apply for a building permit in Town of Hillsboro, Maryland. Permit authority, application steps, fees, and inspection requirements.

Avg processing
Not published
Last verified
April 2026
On this page 6
§ 01

Permit authority

Town of Hillsboro (Town Office / Mayor and Council)

Street address
Hillsboro, MD 21641
Coverage
Hillsboro is a small incorporated town located along Tuckahoe Creek. Properties within the Critical Area (within 1,000 feet of Tuckahoe Creek tidal portions and tributaries) are subject to Critical Area Program requirements. A Maryland DNR Critical Area review found that most of the town's Critical Area land is designated as Limited Development Area (LDA) with a small area of Resource Conservation Area (RCA) wetlands. The town's own permitting capacity is limited; applicants should contact the town and also contact the Caroline County Department of Planning, Codes and Engineering to confirm whether town or county jurisdiction applies for their specific project.
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Hillsboro

The town uses a building permit form for all local building permissions. Contact the town to confirm specific trigger thresholds.

State code exemptions apply
  • Exempt State code exemptions apply

Note: Contact the town and confirm whether Critical Area review is required for exempt-from-permit activities on waterfront properties

Required documents
  • Building Permit form
  • Site plan and construction drawings as required
  • Critical Area review documents if applicable
Building code
Maryland Building Performance Standards (2021 IBC/IRC, 2020 NEC) with state amendments; local ordinances
Permit validity
Not separately published; confirm with the town
Owner-builder
Not separately published
Contractor requirements
MHIC for home improvement work; HBR for new residential construction; Maryland trade licenses for electrical, plumbing, and mechanical work
§ 03

Application process

Typical processing: Not published

  1. 01
    Download the Building Permit form from https://hillsboromd.com/forms/. The form is described as being used for all local building permissions including sheds, fences, etc.
  2. 02
    Complete the form and assemble any required supporting documents.
  3. 03
    Contact the town through the website or by confirming a phone contact to determine submission instructions and fees.
  4. 04
    For any work on properties in the Critical Area (along Tuckahoe Creek), additionally contact the Caroline County Critical Area Program staff (Matt Kaczynski, 410-479-8100) before starting work.

Typical processing time: Not published

Source: Town of Hillsboro (Town Office / Mayor and Council) ↗

§ 04

Fee schedule

Hillsboro building permit fees

Fee type
Amount
01
Permit fee formula
Not published in available public sources; confirm with the town
§ 05

Required inspections

Scheduling and sequence

How to schedule
§ 06

Frequently asked

Common questions about Hillsboro permits

01 Do I need a building permit in Hillsboro, MD?
The town uses a building permit form for all local building permissions. Contact the town to confirm specific trigger thresholds.
02 How much does a building permit cost in Hillsboro, MD?
Building permit fees in Hillsboro, MD are set by the local building department and vary by project type and valuation. Fees are calculated as: Not published in available public sources; confirm with the town.
03 How do I apply for a building permit in Hillsboro, MD?
To apply for a building permit in Hillsboro, MD, follow these steps: 1. Download the Building Permit form from https://hillsboromd.com/forms/. The form is described as being used for all local building permissions including sheds, fences, etc. 2. Complete the form and assemble any required supporting documents. 3. Contact the town through the website or by confirming a phone contact to determine submission instructions and fees. 4. For any work on properties in the Critical Area (along Tuckahoe Creek), additionally contact the Caroline County Critical Area Program staff (Matt Kaczynski, 410-479-8100) before starting work.
04 How long does it take to get a building permit in Hillsboro, MD?
Building permit processing times in Hillsboro, MD typically run Not published. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Hillsboro, MD?
Not all construction work requires a permit in Hillsboro, MD. The following work is generally exempt: State code exemptions apply. Note: Contact the town and confirm whether Critical Area review is required for exempt-from-permit activities on waterfront properties When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Hillsboro, MD?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Hillsboro, MD via: Contact the town through https://hillsboromd.com/, For Critical Area inspection questions, contact Caroline County Critical Area Program at 410-479-8100.
last verified April 2026 source Town of Hillsboro (Town Office / Mayor and Council) ↗ entry id permits/maryland/caroline/hillsboro

Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Hillsboro (Town Office / Mayor and Council) before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Caroline County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Caroline County jurisdictions →