§ 01

Permit authority

Planning Board / Code Enforcement, Town of Machiasport

Street address
Municipal Complex, 3 Bayview Drive, PO Box 267, Machiasport, ME 04655
Coverage
Town of Machiasport; population approximately 1,300. Coastal community on the Machias River and Machias Bay. Below 4,000 MUBEC threshold.
Online portal
Permit portal
PDF / in-person
§ 02

When a permit is required

Permit triggers and exempt work for Machiasport

New construction; altering or adding beyond original footprint; replacing, removing, or relocating a building or structure; adding or erecting a temporary building/structure for more than 90 days; adding a porch or deck greater than 25 sq ft; installing a manufactured home/mobile home/trailer; building a free-standing structure over 120 sq ft; installing a driveway or culvert; installing an outdoor wood-fired furnace; adding bedrooms; roofing that increases volume; building a foundation; constructing a windmill or tower; changing the use of a property.

Confirm with Planning Board / CEO; see General Requirements for items explicitly requiring permits.
  • Exempt Confirm with Planning Board / CEO; see General Requirements for items explicitly requiring permits.
Building code
MUBEC enforcement voluntary given population; confirm with town. Local ordinances enforced.
Owner-builder
Confirm with CEO.
Contractor requirements
Licensed Maine electrician for electrical; licensed Maine plumber for plumbing. CEO inspects plumbing, electrical systems, construction, and maintenance.
§ 03

Application process

Typical processing: Aligned with monthly Planning Board schedule.

  1. 01
    Contact Planning Board / CEO to determine if permit is required.
  2. 02
    Obtain application from town documents page or town office.
  3. 03
    Submit application for Planning Board review.
  4. 04
    Planning Board meets first Thursday of each month at 5:00 p.m.
  5. 05
    Permit issued after Planning Board approval; post at job site.
  6. 06
    CEO monitors for code violations during construction.
  7. 07
    Final inspection upon completion.

Typical processing time: Aligned with monthly Planning Board schedule.

Source: Planning Board / Code Enforcement, Town of Machiasport ↗

§ 04

Required inspections

Scheduling and sequence

Scheduling deadline
Contact CEO through town office

Typical sequence: Contact CEO.

§ 05

Frequently asked

Common questions about Machiasport permits

01 Do I need a building permit in Machiasport, ME?
New construction; altering or adding beyond original footprint; replacing, removing, or relocating a building or structure; adding or erecting a temporary building/structure for more than 90 days; adding a porch or deck greater than 25 sq ft; installing a manufactured home/mobile home/trailer; building a free-standing structure over 120 sq ft; installing a driveway or culvert; installing an outdoor wood-fired furnace; adding bedrooms; roofing that increases volume; building a foundation; constructing a windmill or tower; changing the use of a property.
02 How do I apply for a building permit in Machiasport, ME?
To apply for a building permit in Machiasport, ME, follow these steps: 1. Contact Planning Board / CEO to determine if permit is required. 2. Obtain application from town documents page or town office. 3. Submit application for Planning Board review. 4. Planning Board meets first Thursday of each month at 5:00 p.m. 5. Permit issued after Planning Board approval; post at job site. 6. CEO monitors for code violations during construction. 7. Final inspection upon completion.
03 How long does it take to get a building permit in Machiasport, ME?
Building permit processing times in Machiasport, ME typically run Aligned with monthly Planning Board schedule.. Timelines can vary based on project complexity and current department workload.
04 What work is exempt from building permits in Machiasport, ME?
Not all construction work requires a permit in Machiasport, ME. The following work is generally exempt: Confirm with Planning Board / CEO; see General Requirements for items explicitly requiring permits.. When in doubt, confirm with the local building department before starting work.
last verified April 2026 source Planning Board / Code Enforcement, Town of Machiasport ↗ entry id permits/maine/washington/machiasport

Educational reference. Permit rules and fees change — confirm current requirements directly with Planning Board / Code Enforcement, Town of Machiasport before applying. Jaspector is not legal advice.