How to apply for a building permit in Town of Abita Springs, Louisiana. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Planning and Zoning and Permitting, Town of Abita Springs

Street address
72077 Live Oak Street, Abita Springs, LA 70420
Coverage
Covers properties within the Town of Abita Springs.
Online portal
Town of Abita Springs Building Permits
Department-based
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Abita Springs

Town materials require permits for residential construction, additions, remodels, pools, fences over 7 feet, solar panels, land clearing, stormwater and drainage work, and related utility and right-of-way work.

Note: No broad consolidated exempt-work list was clearly posted. Public fee sheet implies that fences over 7 feet require a permit, but it does not expressly say that lower fences are exempt, so confirm fence exemptions with the town before construction.

Required documents
  • Completed permit application
  • Contractor registration and insurance
  • Property deed or proof of ownership
  • Signed building agreement
  • 911 assigned address form
  • Variance or re-sub approval if applicable
  • State highway approval for state roads
  • Survey showing flood zone
  • Form spot
  • Electronic plan set stamped by a design professional
  • Plot plan
  • Design criteria showing wind speed, flood zone, hurricane clips, strapping, shingle and siding application
  • Foundation plans stamped by a design professional or civil engineer
  • Stormwater agreement and site plan
  • Sediment control and drainage plan
  • Right of way use or culvert permit if applicable
Building code
Public town materials require plans to show current design criteria but do not clearly publish a single updated code-adoption summary page with edition numbers.
Permit validity
Town ordinance states building permits are valid for one year after issuance and may be renewed only once for an additional one-year period.
Owner-builder
Public residential guidance does not clearly publish a separate owner-builder affidavit.
Contractor requirements
Residential guide states contractor registration must be complete for all contractors and subcontractors, and they must be state or parish licensed and registered with the town and show proof of insurance.

Source: Planning and Zoning and Permitting, Town of Abita Springs ↗

§ 03

Application process

Typical processing: The town code states building permit applications are to be reviewed and acted upon within 5 working days from submission.

  1. 01
    Confirm zoning first, especially whether the property is in the Historic Overlay and needs Historic Commission approval.
  2. 02
    Complete the permit application and contractor registration requirements.
  3. 03
    Assemble the required ownership, survey, form spot, plot plan, drainage, and stormwater documents and email an electronic plan set to the Planning and Zoning Director.
  4. 04
    Submit any related land clearing, tree removal, drainage, stormwater, and right-of-way or culvert applications that apply to the site.
  5. 05
    Pay plan review, permit, trade, and inspection package fees.
  6. 06
    Complete the required inspections and provide pre-pour and post-construction elevation certificates where floodplain rules apply.

Typical processing time: The town code states building permit applications are to be reviewed and acted upon within 5 working days from submission.

Source: Planning and Zoning and Permitting, Town of Abita Springs ↗

§ 04

Fee schedule

Abita Springs building permit fees

Fee type
Amount
01
Minimum permit fee
Plan review is $0.15 per square foot with a $100 minimum. Building permit for new construction or addition starts at $125 plus $0.25 per square foot. Remodel or renovation starts at $75 plus $0.25 per square foot.
02
Plan check fee
$0.15 per square foot of total footprint, minimum $100.
03
Permit fee formula
Mixed but largely square-foot and flat-fee based. Trade permits are flat at $75 per trade. Inspection package is flat-fee based.
04
Trade permit fee
$75 per trade.
05
Reinspection fee
Failed inspections are $75 for building and land clearing. Drainage and stormwater failed inspections are $50.

Public-facing sources reviewed did not clearly post portal payment or card-processing rules.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • 985-892-0711 option 4 (phone)

Typical sequence: Temp pole and toilet; plumbing underground; foundation or piers; certified test meter; all rough-ins or closed wall together; all finals together; additional natural gas inspections where applicable.

Source: Planning and Zoning and Permitting, Town of Abita Springs ↗

§ 06

Frequently asked

Common questions about Abita Springs permits

01 Do I need a building permit in Abita Springs, LA?
Town materials require permits for residential construction, additions, remodels, pools, fences over 7 feet, solar panels, land clearing, stormwater and drainage work, and related utility and right-of-way work.
02 How much does a building permit cost in Abita Springs, LA?
Building permit fees in Abita Springs, LA are set by the local building department and vary by project type and valuation. The minimum permit fee is Plan review is $0.15 per square foot with a $100 minimum. Building permit for new construction or addition starts at $125 plus $0.25 per square foot. Remodel or renovation starts at $75 plus $0.25 per square foot.. Fees are calculated as: Mixed but largely square-foot and flat-fee based. Trade permits are flat at $75 per trade. Inspection package is flat-fee based.. Plan check fee: $0.15 per square foot of total footprint, minimum $100..
03 How do I apply for a building permit in Abita Springs, LA?
To apply for a building permit in Abita Springs, LA, follow these steps: 1. Confirm zoning first, especially whether the property is in the Historic Overlay and needs Historic Commission approval. 2. Complete the permit application and contractor registration requirements. 3. Assemble the required ownership, survey, form spot, plot plan, drainage, and stormwater documents and email an electronic plan set to the Planning and Zoning Director. 4. Submit any related land clearing, tree removal, drainage, stormwater, and right-of-way or culvert applications that apply to the site. 5. Pay plan review, permit, trade, and inspection package fees. 6. Complete the required inspections and provide pre-pour and post-construction elevation certificates where floodplain rules apply.
04 How long does it take to get a building permit in Abita Springs, LA?
Building permit processing times in Abita Springs, LA typically run The town code states building permit applications are to be reviewed and acted upon within 5 working days from submission.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Abita Springs, LA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Abita Springs, LA via: 985-892-0711 option 4.
last verified April 2026 source Planning and Zoning and Permitting, Town of Abita Springs ↗ entry id permits/louisiana/st-tammany/abita-springs

Educational reference. Permit rules and fees change — confirm current requirements directly with Planning and Zoning and Permitting, Town of Abita Springs before applying. Jaspector is not legal advice.