When a permit is required
Permit triggers and exempt work for Taylorsville
A construction permit is required for any building or structure erected, moved, added to, or structurally altered within the City of Taylorsville.
- Exempt Recurring maintenance regardless of cost
- Exempt Agricultural structures (non-dwelling) on plots of five acres or more
- Exempt Alterations to existing buildings with a replacement value of $500 or less
- Exempt Construction of service connections to publicly owned and operated utilities
- Exempt Grading, streets, ditch digging, cutting/filling, and similar site improvements done before building development
- Exempt Installation of required improvements shown on an approved preliminary subdivision or planned development plat
- Exempt Agricultural uses that do not include dwelling units
- Exempt Agricultural structures on 10 or more acres (with Agricultural Building Permit Exemption Affidavit)
Note: Confirm applicability of exemptions with Spencer County Planning & Zoning; exemptions may not release applicants from zoning or floodplain overlay requirements.
- Completed building permit application
- Two sets of construction plans
- Plot plan with setback measurements
- Health department approval for water/septic
- Worker's compensation proof or state exemption affidavit
- Proof of contractor occupation/business license
- Subcontractor list
- Local stream/floodplain permit (if waterway work)
- Building code
- 2018 Kentucky Building Code (KBC) and 2018 Kentucky Residential Code (KRC)
- Permit validity
- Permit must be picked up and posted within 15 days of issuance. Administrator must act on applications within six months.
- Owner-builder
- Owner or contractor may sign the application but must certify compliance with easements, zoning, and Kentucky worker's compensation/unemployment requirements (KRS Chapter 342 and 341) or file the state affidavit of exemption with the Office of Worker's Claims.
- Contractor requirements
- Every contractor must provide proof of a county occupation/business license and comply with KRS Chapter 342 (worker's compensation) and KRS Chapter 341 (unemployment insurance).
Application process
Typical processing: Within six months of application per Article XI of the zoning code.
- 01 Determine permit type (residential, commercial, agricultural, sign, demolition, change of occupancy).
- 02 Complete the appropriate building permit application form.
- 03 Prepare two sets of construction plans and a plot plan with dimensions and setback measurements.
- 04 Obtain health department approval for water/septic systems if applicable.
- 05 Provide proof of worker's compensation coverage or state exemption affidavit.
- 06 Provide proof of contractor occupation/business license.
- 07 Prepare subcontractor list.
- 08 Deliver completed packet with fees in person at 220 Main Cross Street, Taylorsville.
- 09 Planning & Zoning Administrator reviews for zoning compliance; Building Inspector issues permit.
- 10 Post permit visibly from the road within 15 days of issuance.
- 11 Schedule inspections (footer, framing, final) by calling Building Inspector Steve Clark at 502-643-9039 at least 24 hours in advance.
- 12 Pass final inspection before occupying the structure.
Typical processing time: Within six months of application per Article XI of the zoning code.
Fee schedule
Taylorsville building permit fees
Construction permit fees: checks/cash to Spencer County Planning & Zoning. Inspection fees: checks/cash to Steve Clark, LLC. CertifiedPayments online option available (Bureau Code 1391112).
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- Building Inspector Steve Clark (phone)
- Scheduling deadline
- Call at least 24 hours before the requested inspection date.
- Inspection hours
- Planning & Zoning office: Monday-Friday, 8:00 AM to 4:00 PM. State plumbing inspector: Tuesday and Thursday mornings.
Typical sequence: Typical sequence: footer (prior to pouring concrete), framing (before insulation), and final (finished structure with drainage and sump pump placement).
Frequently asked
Common questions about Taylorsville permits
01 Do I need a building permit in Taylorsville, KY? ▸
02 How much does a building permit cost in Taylorsville, KY? ▸
03 How do I apply for a building permit in Taylorsville, KY? ▸
04 How long does it take to get a building permit in Taylorsville, KY? ▸
05 What work is exempt from building permits in Taylorsville, KY? ▸
06 How do I schedule a building inspection in Taylorsville, KY? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Taylorsville-Spencer County Joint Planning & Zoning Commission / Spencer County Planning & Zoning Building Code Enforcement before applying. Jaspector is not legal advice.