When a permit is required
Permit triggers and exempt work for Perry County
Any work subject to the Kentucky Building Code (new buildings, additions, major alterations, or regulated systems) requires a permit, regardless of contractor status.
Note: County-level exemptions are not published online; consult the Kentucky Building Code exemption section when planning unregulated work.
- Scaled construction drawings
- Use descriptions
- Required environmental approvals from the Perry County Health Department
- Building code
- Statewide adoption of the Kentucky Building Code, Residential Code, Plumbing Code, and Standards of Safety (815 KAR 7:120 and related regulations).
- Permit validity
- Not stated publicly; assume the standard six-month window from local/state codes unless an extension is authorized.
- Owner-builder
- Not uniquely addressed locally; the Kentucky code treats owner-builders like other applicants.
- Contractor requirements
- Electrical, plumbing, and mechanical work must be performed or inspected by licensed tradespeople and certified inspectors; the local contract inspector enforces those standards.
Application process
Typical processing: 2–3 weeks for plan reviews per Resolution 07012025, assuming complete materials.
- 01 Call the Fiscal Court at (606) 439-1816 to connect with the contracted inspector (Wes Finley, cell 606-416-4182) and request the application checklist.
- 02 Submit drawings, scope statements, and state-required approvals (e.g., potable water/sewer sign-off) to the inspector for plan review under the Kentucky Building Code (815 KAR 7:120).
- 03 The inspector grants or denies the permit locally; Fiscal Court targets review windows of roughly two to three weeks after Resolution 07012025.
- 04 Once issued, schedule inspections directly with the inspector; state law governs inspection stages and occupancy approvals.
Typical processing time: 2–3 weeks for plan reviews per Resolution 07012025, assuming complete materials.
Required inspections
Scheduling and sequence
- Wes Finley (contracted inspector) – (606) 416-4182 (phone)
- Inspection hours
- Early Tuesday and Friday mornings; confirm availability when calling
Typical sequence: Follows the Kentucky Building Code stages (footing/foundation, framing, systems, final) under KRS 198B, with the inspector certifying compliance before occupancy.
Frequently asked
Common questions about unincorporated Perry County permits
01 Do I need a building permit in unincorporated Perry County, KY? ▸
02 How do I apply for a building permit in unincorporated Perry County, KY? ▸
03 How long does it take to get a building permit in unincorporated Perry County, KY? ▸
04 How do I schedule a building inspection in unincorporated Perry County, KY? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Perry County Fiscal Court / Judge Executive's Office with contracted local building inspector before applying. Jaspector is not legal advice.