How to apply for a building permit in City of Tollesboro, Kentucky. Permit authority, application steps, fees, and inspection requirements.

Avg processing
Not published.
Last verified
April 2026
On this page 6
§ 01

Permit authority

Lewis County Judge Executive's office together with Kentucky Department of Housing, Buildings and Construction (DHBC)

Street address
112 Second St., Rm. 201, Vanceburg, KY 41179
Coverage
Building permits for the City of Tollesboro. DHBC covers all counties lacking a local inspector, including the town of Tollesboro.
§ 02

When a permit is required

Permit triggers and exempt work for Tollesboro

KRS 67.410 covers building, remodeling, and alteration work. The DHBC sheet names DHBC as the inspector for counties without local officials.

Note: No exempt-work list is published for Tollesboro; check with the state inspector before starting minor work.

Required documents
  • Site, floor, cross section, and floor framing plans
  • Contractor and subcontractor details
  • Insurance documentation
  • Owner/contractor information and owner authorization (if applicant is not owner)
  • Estimated construction cost
  • Subcontractor rosters
Building code
International Residential Code and Kentucky Residential Code apply.
Permit validity
Not published; verify with DHBC.
Owner-builder
The owner must authorize another applicant.
Contractor requirements
Contractors must meet KRS 198B.060 and KRS 342 insurance mandates. Workers' compensation and unemployment coverage is required, and DHBC must be informed of subcontractor roster changes.
§ 03

Application process

Typical processing: Not published.

  1. 01
    Contact Wade Trimble (state building inspector) to confirm permit requirements for Tollesboro.
  2. 02
    Coordinate with the Lewis County Judge Executive's office to route documentation to DHBC and assign trade inspectors.
  3. 03
    Submit the plans, insurance proof, subcontractor list, and fees, then schedule inspections with the listed trade inspectors.
  4. 04
    Begin work only after DHBC issues the permit.

Typical processing time: Not published.

Source: Lewis County Judge Executive's office together with Kentucky Department of Housing, Buildings and Construction (DHBC) ↗

§ 04

Fee schedule

Tollesboro building permit fees

Fee type
Amount
01
Permit fee formula
Not detailed; estimated construction cost is gathered.

Fee must accompany the application; clarify processing with DHBC.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • Wade Trimble (State Building Inspector) (phone)
  • wade.trimble@ky.gov (email)
Inspection hours
Tuesday 8:00–9:30 a.m. EST and weekday 8:00–9:30 a.m. at the Lewis County Health Department for environmentalist.

Typical sequence: DHBC lists HVAC, plumbing, elevator, and boiler inspectors; confirm the order with the assigned inspector.

Source: Lewis County Judge Executive's office together with Kentucky Department of Housing, Buildings and Construction (DHBC) ↗

§ 06

Frequently asked

Common questions about Tollesboro permits

01 Do I need a building permit in Tollesboro, KY?
KRS 67.410 covers building, remodeling, and alteration work. The DHBC sheet names DHBC as the inspector for counties without local officials.
02 How much does a building permit cost in Tollesboro, KY?
Building permit fees in Tollesboro, KY are set by the local building department and vary by project type and valuation. Fees are calculated as: Not detailed; estimated construction cost is gathered..
03 How do I apply for a building permit in Tollesboro, KY?
To apply for a building permit in Tollesboro, KY, follow these steps: 1. Contact Wade Trimble (state building inspector) to confirm permit requirements for Tollesboro. 2. Coordinate with the Lewis County Judge Executive's office to route documentation to DHBC and assign trade inspectors. 3. Submit the plans, insurance proof, subcontractor list, and fees, then schedule inspections with the listed trade inspectors. 4. Begin work only after DHBC issues the permit.
04 How long does it take to get a building permit in Tollesboro, KY?
Building permit processing times in Tollesboro, KY typically run Not published.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Tollesboro, KY?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Tollesboro, KY via: Wade Trimble (State Building Inspector), wade.trimble@ky.gov.

Educational reference. Permit rules and fees change — confirm current requirements directly with Lewis County Judge Executive's office together with Kentucky Department of Housing, Buildings and Construction (DHBC) before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Lewis County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Lewis County jurisdictions →