When a permit is required
Permit triggers and exempt work for Hardin County
HCPDC requires building and electrical permits and inspections for all new construction, additions, and remodeling.
Note: No countywide public exempt-work list was located. Public materials frame permits as required for new construction, additions, and remodeling. Verify edge cases with HCPDC before starting work.
- Residential building/zoning permit application
- Building affidavit
- Deed
- Plot plan showing distances to property lines and structures
- Encroachment permit for new and existing private access off state and county roads
- On-site sewage evaluation for dwellings or structures with plumbing
- Construction plans for all new houses
- Plan review submittal for houses with 2,000 or more square feet of roofed area
- Floodplain or stream construction approvals where applicable
- Building code
- 2018 Kentucky Residential Code
- Permit validity
- If no inspections are requested for 180 days or more, the permit is deemed inactive and closed; new application and fees are required to reopen and complete the project.
- Owner-builder
- Homeowner electrical waiver and owner electrical affidavit are published; building packet includes affidavit and workers compensation compliance statement. Homeowners may use waiver forms where allowed.
- Contractor requirements
- Electrical contractors must hold electrical contractor and master electrician credentials for the HCPDC program. Building affidavit requires workers compensation and unemployment insurance compliance under KRS 198B.060(10).
Application process
Typical processing: 15 working days for residential plan review on houses over 2,000 square feet of roofed area and for commercial plan review
- 01 Confirm whether the project needs a permit; HCPDC requires building and electrical permits for all new construction, additions, and remodeling.
- 02 Assemble the required permit packet, including building permit application, building affidavit, plot plan, deed, and any required encroachment, septic, floodplain, or stream construction approvals.
- 03 Submit the permit packet in person at the HCPDC office. All building and electrical permits must be submitted in person, except registered certified electrical contractors using the portal.
- 04 If plans are required, allow plan review time. New houses over 2,000 square feet of roofed area and all commercial projects require plan review with an estimated 15 working days.
- 05 After issuance, call or use the inspection request tools for footing, framing, and final inspections before occupancy.
Typical processing time: 15 working days for residential plan review on houses over 2,000 square feet of roofed area and for commercial plan review
Fee schedule
Hardin County building permit fees
Applicants must submit permits in person; checks are made payable to Kentucky Building Code on the residential application
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- (270) 769-5479 (phone)
- Inspection hours
- Monday through Friday, 8:00 a.m. to 4:30 p.m.
Typical sequence: Typical sequence: footing, framing, final
Frequently asked
Common questions about unincorporated Hardin County permits
01 Do I need a building permit in unincorporated Hardin County, KY? ▸
02 How much does a building permit cost in unincorporated Hardin County, KY? ▸
03 How do I apply for a building permit in unincorporated Hardin County, KY? ▸
04 How long does it take to get a building permit in unincorporated Hardin County, KY? ▸
05 How do I schedule a building inspection in unincorporated Hardin County, KY? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Hardin County Planning and Development Commission before applying. Jaspector is not legal advice.