§ 01

Permit authority

City of Catlettsburg Building Inspector

Street address
2611 Louisa Street, Catlettsburg, KY 41129
Coverage
All permits, code enforcement, and occupancy control within Catlettsburg city limits.
§ 02

When a permit is required

Permit triggers and exempt work for Catlettsburg

All excavation, construction, movement, or alteration of any building (accessory or otherwise) requires a permit before work begins.

Note: No public exempt-work list is supplied; the code states the inspector must approve all excavation and construction, so every project needs a permit.

Required documents
  • Dimensional sketch or scale plan that outlines all buildings on the lot
  • Proposed work description
  • Intended use designation
  • Any other information the inspector requests to verify ordinance compliance
Building code
2018 Kentucky Building Code (2015 International Building Code plus Kentucky amendments) and 2018 Kentucky Residential Code
Permit validity
Not specified in the ordinance; verify with the Building Inspector when the permit is issued.
Owner-builder
The code applies uniformly regardless of whether the applicant is the owner or a contractor—only a compliant permit is required.
Contractor requirements
All construction must comply with the 2018 Kentucky Building and Residential Codes (statewide 2015 IBC/IRC cycle); licensed trades must handle regulated work.

Source: City of Catlettsburg Building Inspector ↗

§ 03

Application process

Typical processing: The code requires the inspector to grant or deny permits within a reasonable time frame but does not list a specific deadline.

  1. 01
    Submit a permit application together with a dimensional sketch or scale plan showing the shape, size, height, location, and existing/intended use of every structure on the lot.
  2. 02
    The Building Inspector reviews the submission for compliance with the city's ordinances.
  3. 03
    If everything conforms, the inspector issues the permit; if refused, the inspector must explain the cause in writing and mail notice to the applicant.
  4. 04
    Display the permit on site, allow inspections during construction, and request a final inspection once the project is ready for occupancy.
  5. 05
    Within three days of notifying the inspector that the building or part thereof is ready, the inspector conducts a final inspection and issues a Certificate of Occupancy if code compliance is met.

Typical processing time: The code requires the inspector to grant or deny permits within a reasonable time frame but does not list a specific deadline.

Source: City of Catlettsburg Building Inspector ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • 606-739-4533 (phone)
Inspection hours
Monday-Friday, 8:00 AM to 4:00 PM

Typical sequence: After the permit is issued, the inspector visits the site during construction; once notified the work is ready, the inspector conducts a final review and issues the Certificate of Occupancy if the structure complies.

Source: City of Catlettsburg Building Inspector ↗

§ 05

Frequently asked

Common questions about Catlettsburg permits

01 Do I need a building permit in Catlettsburg, KY?
All excavation, construction, movement, or alteration of any building (accessory or otherwise) requires a permit before work begins.
02 How do I apply for a building permit in Catlettsburg, KY?
To apply for a building permit in Catlettsburg, KY, follow these steps: 1. Submit a permit application together with a dimensional sketch or scale plan showing the shape, size, height, location, and existing/intended use of every structure on the lot. 2. The Building Inspector reviews the submission for compliance with the city's ordinances. 3. If everything conforms, the inspector issues the permit; if refused, the inspector must explain the cause in writing and mail notice to the applicant. 4. Display the permit on site, allow inspections during construction, and request a final inspection once the project is ready for occupancy. 5. Within three days of notifying the inspector that the building or part thereof is ready, the inspector conducts a final inspection and issues a Certificate of Occupancy if code compliance is met.
03 How long does it take to get a building permit in Catlettsburg, KY?
Building permit processing times in Catlettsburg, KY typically run The code requires the inspector to grant or deny permits within a reasonable time frame but does not list a specific deadline.. Timelines can vary based on project complexity and current department workload.
04 How do I schedule a building inspection in Catlettsburg, KY?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Catlettsburg, KY via: 606-739-4533.
last verified April 2026 source City of Catlettsburg Building Inspector ↗ entry id permits/kentucky/boyd/catlettsburg

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Catlettsburg Building Inspector before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Boyd County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Boyd County jurisdictions →