On this page 6
When a permit is required
Permit triggers and exempt work for Smith Center
Required to erect, construct, enlarge, or improve any building or structure in the city. Fences also require a permit.
- Exempt Addition, repair, or replacement of exterior and interior finishing materials such as shingles, siding, paneling, doors, and windows.
- Exempt Construction of sidewalks.
- Exempt Construction of patios.
- Exempt Redecorating.
- Exempt Some roofing exceptions apply for owner-performed work and certain exempt contractors under state law.
- Written application
- Project details
- Contractor name and address
- Drawings or plans if requested
- Roofer registration info if roofing work
- Renovation certification for pre-1978 work that disturbs regulated painted surfaces
- Building code
- Smith Center Code of Ordinances, Chapter IV, Buildings and Construction, including Article 2 Building Code and references to the International Building Code.
- Permit validity
- Permit valid for not more than six months unless work has commenced within that period.
- Owner-builder
- Owners may do their own residential work for personal use and permanent occupancy, subject to inspector approval and permit requirements; work must be done without compensation and generally without helper labor except a city-licensed contractor.
- Contractor requirements
- City-licensed contractor required in many cases; roofing work must include roofer registration number and certain state registration or exemption proof; pre-1978 renovation work must comply with applicable certification rules.
Application process
Application → plan check → issuance → inspection → final
- 01 Complete the written building permit application from the city website or City Clerk office.
- 02 Provide required project details, including owner, location, work description, dimensions, occupancy class, materials, estimated cost, start date, completion date, and contractor info.
- 03 If owner is doing the work, satisfy the Building Inspector that the owner will perform the work personally.
- 04 If needed, submit drawings, descriptions, or full architectural and engineering plans.
- 05 City reviews the application, verifies any required certifications, and issues the permit if approved.
Fee schedule
Smith Center building permit fees
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- Notify the Chief Building Official or Building Inspector; inspection requests are made after completion and at key stages of construction. (phone)
- Inspection hours
- Building Inspector may enter any building, structure, or premises at any reasonable hour.
Typical sequence: Layout and setback inspection after site marking; foundation and footing inspection before pour; additional successive-stage inspections as directed; final inspection after completion; certificate of approval may be issued for occupancy and use.
Frequently asked
Common questions about Smith Center permits
01 Do I need a building permit in Smith Center, KS? ▸
02 How much does a building permit cost in Smith Center, KS? ▸
03 How do I apply for a building permit in Smith Center, KS? ▸
04 What work is exempt from building permits in Smith Center, KS? ▸
05 How do I schedule a building inspection in Smith Center, KS? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with City Clerk / City Hall / Building Official. before applying. Jaspector is not legal advice.