Permit Authority
Tippecanoe County annual report says Shadeland issued its own building permits until October 2021, after which County Building Commission began that work. Current Shadeland public pages still require a local Start Building Permit Form and zoning review through town hall.
- Department
- Tippecanoe County Building Commission for building permit issuance; Town of Shadeland Planning and Zoning for town review
- Address
- County permit office: 20 North 3rd Street, Lafayette, IN 47901; town office: 5220 Old State Road 25 N, Lafayette, IN 47905
- Phone
- County 765-423-9225; town 765-474-6533
Online Permit Portal
Platform: Tippecanoe County Online Permit Applications and Information • Account required: No • Submission: In-person only
Additional resources:
Application Process
- Start with the Town of Shadeland Planning and Zoning page and complete the Start Building Permit Form.
- Submit the completed form to the town manager by email or to town hall, with proposed site plan and building plans. If the property is in an HOA, the HOA must sign off before the town will process the permit start form.
- After town review, route the actual building permit issuance through Tippecanoe County Building Commission under the county's current post-2021 permit structure.
- Submit the county permit packet with plans and any project-specific approvals.
- Pay county fees, wait for county review, and then schedule county inspections.
General Requirements
Required Documents
- Town start form
- Proposed site plan and building plans
- HOA signoff if applicable
- County permit packet and project-specific approvals
- Building code
- County-administered Indiana code enforcement for building permits; Shadeland municipal code remains relevant for local land-use and town standards.
- Contractor requirements
- County bond rules apply for contractors on the county-issued permit.
Fees
- Minimum permit fee
- County minimum permit fee is $75.00 for the listed square-foot categories, plus filing fee
- Permit fee formula
- County mixed square-foot and flat-fee schedule applies for the building permit itself.
Fees change. Verify current amounts at the official fee schedule.
Work That Does NOT Require a Permit
- Fences do not require a building permit
- Above-ground pools below 42 inches do not require a permit
Inspections
How to Schedule
- 765-423-9225 (phone)
- Scheduling deadline
- At least 24 hours notice required
- Inspection hours
- Monday through Friday, 8:00 AM to 4:30 PM
Typical inspection sequence: County inspection schedule applies.
Additional Resources
- Building code: County-administered Indiana code enforcement for building permits; Shadeland municipal code remains relevant for local land-use and town standards.
- Zoning information: View zoning info
- Shadeland Municipal Code
- Fence Brochure
- License lookup guide: Indiana Contractor License Requirements
- Contract template: Indiana Homeowner-Contractor Agreement
- Indiana hub: Indiana Contractor License & Permit Hub
Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Tippecanoe County Building Commission for building permit issuance; Town of Shadeland Planning and Zoning for town review before applying.
Frequently Asked Questions
Town of Shadeland Building Permit FAQ
- How much does a building permit cost in Town of Shadeland, IN?
- The minimum permit fee is County minimum permit fee is $75.00 for the listed square-foot categories, plus filing fee. Fees are calculated as: County mixed square-foot and flat-fee schedule applies for the building permit itself..
- How do I apply for a building permit in Town of Shadeland, IN?
- 1. Start with the Town of Shadeland Planning and Zoning page and complete the Start Building Permit Form. 2. Submit the completed form to the town manager by email or to town hall, with proposed site plan and building plans. If the property is in an HOA, the HOA must sign off before the town will process the permit start form. 3. After town review, route the actual building permit issuance through Tippecanoe County Building Commission under the county's current post-2021 permit structure. 4. Submit the county permit packet with plans and any project-specific approvals. 5. Pay county fees, wait for county review, and then schedule county inspections.
- What work is exempt from building permits in Town of Shadeland, IN?
- The following work is generally exempt: Fences do not require a building permit; Above-ground pools below 42 inches do not require a permit.
- How do I schedule a building inspection in Town of Shadeland, IN?
- Inspections can be scheduled via: 765-423-9225. At least 24 hours notice required.
Need help with your project?
Navigating permits in Town of Shadeland can be complicated.
Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.
Learn how Jaspector worksOther cities in Tippecanoe County
View all Tippecanoe County jurisdictions →