When a permit is required
Permit triggers and exempt work for Cass County
Required when occupying or using land; constructing, reconstructing, moving, altering, or enlarging a structure; changing use; or changing a nonconforming use.
- Exempt Water management and use facilities
- Exempt Certain yard improvements
- Exempt Normal plowing and working of land for gardens and yards
- Exempt Trimming or removal of trees and shrubs for maintenance or agricultural purposes
- Exempt Earth movements related to farming and agricultural activity
- Exempt Public and private road construction
- Exempt Installation of utilities
- Exempt Drain tile laying and ditch cleaning
- Exempt Topsoil removal other than mineral excavation
- Exempt Forest management activities
- Exempt Soft-side above-ground pools, hot tubs, spas, and saunas
- Exempt Storage of recreational vehicles and trucks as specified
- Exempt Fences as specified
- Exempt Vending machines as specified
- Site plan
- State design release when required
- Driveway cut approvals when required
- Septic permits when required
- Other outside approvals when required
- Building code
- The public county materials reference compliance with Indiana state building and fire safety rules, but no single county building code adoption line was found.
- Permit validity
- Local Improvement Location Permit and building permit become null and void one year from issuance if not substantially completed.
- Contractor requirements
- The reviewed county materials do not state a separate countywide contractor registration requirement.
Application process
Typical processing: A complete zoning application is generally acted on within 30 days; demolition permit applications are processed within 48 hours.
- 01 Confirm whether the work needs a local Improvement Location Permit and, if applicable, a building permit.
- 02 If the project also needs a state design release, submit plans to the Indiana State Fire Prevention and Building Safety Plan Review first.
- 03 Gather required supporting items such as site plans, driveway cut approvals, septic permits, and any other required outside approvals.
- 04 Submit the local application to the Cass County Planning Department.
- 05 The planning office reviews the application and, if the local standards are met, issues the permit.
- 06 Start work only after permits are issued.
Typical processing time: A complete zoning application is generally acted on within 30 days; demolition permit applications are processed within 48 hours.
Fee schedule
Cass County building permit fees
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
Typical sequence: Permits are issued first, then construction can begin. Inspections are performed during the work and at completion as needed.
Frequently asked
Common questions about unincorporated Cass County permits
01 Do I need a building permit in unincorporated Cass County, IN? ▸
02 How much does a building permit cost in unincorporated Cass County, IN? ▸
03 How do I apply for a building permit in unincorporated Cass County, IN? ▸
04 How long does it take to get a building permit in unincorporated Cass County, IN? ▸
05 What work is exempt from building permits in unincorporated Cass County, IN? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Cass County Planning Department before applying. Jaspector is not legal advice.