When a permit is required
Permit triggers and exempt work for Peoria County
New buildings, additions, alterations, decks > 25 sq. ft., sheds > 200 sq. ft., pools, fences, and demolitions.
- Exempt One-story detached accessory structures < 200 sq. ft. (Building permit exempt, but zoning setbacks apply)
- Exempt Fences under 7 feet (Building permit exempt, but zoning certificate may be required)
- Exempt Retaining walls under 4 feet
- Exempt Decks under 25 sq. ft.
Note: Building permit exempt does not mean exempt from zoning requirements. Confirm edge cases with Peoria County Planning & Zoning before proceeding.
- Application
- Site Plan (must show setbacks)
- Construction Plans
- Illinois Energy Conservation Code compliance
- Building code
- 2018 IRC, 2018 IBC (transitioning to 2021 per state mandate), 2017 NEC, 2021 IL Energy Conservation Code.
- Permit validity
- 6 months to start; 1 year to complete.
- Owner-builder
- Owner-builders are allowed for primary residence.
- Contractor requirements
- State license required for Plumbers and Roofers. Septic contractors must be registered with the Health Dept.
Application process
Typical processing: Residential: 2-3 business days; Commercial: 14 business days.
- 01 Email application and plans to buildingpermits@peoriacounty.org.
- 02 Staff reviews submittal for zoning compliance and code adherence.
- 03 Applicant receives invoice for fees.
- 04 Pay fees online or via phone (309-672-6915).
- 05 Permit issued and emailed to applicant.
Typical processing time: Residential: 2-3 business days; Commercial: 14 business days.
Fee schedule
Peoria County building permit fees
3% service charge for credit cards. $45 Technology Fee added to all permits.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- (309) 672-6915 (phone)
- Inspection hours
- Monday-Friday, 8:30 AM to 4:30 PM
Typical sequence: Typical sequence: Footing, Foundation, Under-slab, Rough-in, Framing, Insulation, Final.
Frequently asked
Common questions about unincorporated Peoria County permits
01 Do I need a building permit in unincorporated Peoria County, IL? ▸
02 How much does a building permit cost in unincorporated Peoria County, IL? ▸
03 How do I apply for a building permit in unincorporated Peoria County, IL? ▸
04 How long does it take to get a building permit in unincorporated Peoria County, IL? ▸
05 What work is exempt from building permits in unincorporated Peoria County, IL? ▸
06 How do I schedule a building inspection in unincorporated Peoria County, IL? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Peoria County Planning & Zoning Department before applying. Jaspector is not legal advice.