How to apply for a building permit in Village of Matherville, Illinois. Permit authority, application steps, fees, and inspection requirements.

Code adoption
2021 IRC/IBC (State mandate).
Avg processing
5-10 business days.
Min. permit fee
$25.00
Last verified
April 2026
On this page 6
§ 01

Permit authority

Village of Matherville Village Hall

Street address
310 S 4th St, Matherville, IL 61263
Coverage
Village of Matherville limits.
Online portal
Village of Matherville Forms
Manual
§ 02

When a permit is required

Permit triggers and exempt work for Matherville

New buildings, additions, fences, and utility connections.

Cosmetic updates
General maintenance
  • Exempt Cosmetic updates
  • Exempt General maintenance
Required documents
  • Application
  • Site plan
Building code
2021 IRC/IBC (State mandate).
Permit validity
1 year.
Owner-builder
Allowed.
Contractor requirements
State licenses for plumbing/roofing.
§ 03

Application process

Typical processing: 5-10 business days.

  1. 01
    Visit Village Hall to obtain building/zoning application.
  2. 02
    Submit application with project details.
  3. 03
    Review by Village Manager (Stephanie McMeekan) or Clerk.
  4. 04
    Approval and fee payment.

Typical processing time: 5-10 business days.

Source: Village of Matherville Village Hall ↗

§ 04

Fee schedule

Matherville building permit fees

Fee type
Amount
01
Minimum permit fee
$25.00
02
Permit fee formula
Flat fees for most residential improvements.

Cash or check at Village Hall.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • Call Village Hall at (309) 754-8814 (phone)
Inspection hours
By appointment

Typical sequence: Final inspection.

§ 06

Frequently asked

Common questions about Matherville permits

01 Do I need a building permit in Matherville, IL?
New buildings, additions, fences, and utility connections.
02 How much does a building permit cost in Matherville, IL?
Building permit fees in Matherville, IL are set by the local building department and vary by project type and valuation. The minimum permit fee is $25.00. Fees are calculated as: Flat fees for most residential improvements..
03 How do I apply for a building permit in Matherville, IL?
To apply for a building permit in Matherville, IL, follow these steps: 1. Visit Village Hall to obtain building/zoning application. 2. Submit application with project details. 3. Review by Village Manager (Stephanie McMeekan) or Clerk. 4. Approval and fee payment.
04 How long does it take to get a building permit in Matherville, IL?
Building permit processing times in Matherville, IL typically run 5-10 business days.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Matherville, IL?
Not all construction work requires a permit in Matherville, IL. The following work is generally exempt: Cosmetic updates; General maintenance. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Matherville, IL?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Matherville, IL via: Call Village Hall at (309) 754-8814.
last verified April 2026 source Village of Matherville Village Hall ↗ entry id permits/illinois/mercer/matherville

Educational reference. Permit rules and fees change — confirm current requirements directly with Village of Matherville Village Hall before applying. Jaspector is not legal advice.