§ 01

Permit authority

Havana Zoning Department

Street address
City Hall, 227 West Main Street, Havana, IL 62644
Coverage
City limits of Havana
§ 02

When a permit is required

Permit triggers and exempt work for Havana

roofing projects, footprint changes, structures over 100 sq. ft., fences, decks, patios, pergolas, and other listed work.

Concrete pads and driveways are not included in the permit process, though runoff rules still apply
  • Exempt Concrete pads and driveways are not included in the permit process, though runoff rules still apply
Required documents
  • completed application, site sketch, project details, contractor and license info where relevant, and stamped prints for C-1 and above new construction.
Building code
Havana states it adopted the 2018 edition of the International Building Code, 2011 NEC, Life Safety Code 2001, IECC, and Illinois Accessibility Code 2018 on the zoning page; the permit form also references the 2020 ICC edition. The public pages conflict, so this should be verified directly with the city before design work.
Owner-builder
form allows owner applicant; no separate public owner-builder policy found.
Contractor requirements
roofing or plumbing license required on the form where applicable; the form also asks for insurance policy information for roofing and plumbing work.
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Determine whether the project is one of the listed permit triggers.
  2. 02
    Complete the building permit application PDF.
  3. 03
    Include site drawing, setbacks, project description, and for new construction in C-1 and above, stamped prints.
  4. 04
    Submit electronically or print and contact zoning.
  5. 05
    Property must be inspected by the zoning officer before issuance.
  6. 06
    Follow up after electronic submission if requested.

Source: Havana Zoning Department ↗

§ 04

Fee schedule

Havana building permit fees

Fee type
Amount
01
Minimum permit fee
$20 for awnings; $30 minimum for residential R-1/R-2 and commercial work up to $5,000
02
Plan check fee
not separately stated
03
Permit fee formula
over $100,000.01, fee is $220 plus $1 per $1,000 of construction cost over $100,000

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • contact zoning department by phone or email to make an appointment for inspection and approval (online)
Inspection hours
city hall hours are not clearly listed on the zoning page; general site shows city administration contact during normal business hours

Typical sequence: application, property inspection, then permit issuance

§ 06

Frequently asked

Common questions about Havana permits

01 Do I need a building permit in Havana, IL?
roofing projects, footprint changes, structures over 100 sq. ft., fences, decks, patios, pergolas, and other listed work.
02 How much does a building permit cost in Havana, IL?
Building permit fees in Havana, IL are set by the local building department and vary by project type and valuation. The minimum permit fee is $20 for awnings; $30 minimum for residential R-1/R-2 and commercial work up to $5,000. Fees are calculated as: over $100,000.01, fee is $220 plus $1 per $1,000 of construction cost over $100,000. Plan check fee: not separately stated.
03 How do I apply for a building permit in Havana, IL?
To apply for a building permit in Havana, IL, follow these steps: 1. Determine whether the project is one of the listed permit triggers. 2. Complete the building permit application PDF. 3. Include site drawing, setbacks, project description, and for new construction in C-1 and above, stamped prints. 4. Submit electronically or print and contact zoning. 5. Property must be inspected by the zoning officer before issuance. 6. Follow up after electronic submission if requested.
04 What work is exempt from building permits in Havana, IL?
Not all construction work requires a permit in Havana, IL. The following work is generally exempt: Concrete pads and driveways are not included in the permit process, though runoff rules still apply. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in Havana, IL?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Havana, IL via: contact zoning department by phone or email to make an appointment for inspection and approval.
last verified April 2026 source Havana Zoning Department ↗ entry id permits/illinois/mason/havana

Educational reference. Permit rules and fees change — confirm current requirements directly with Havana Zoning Department before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Mason County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Mason County jurisdictions →