On this page 6
When a permit is required
Permit triggers and exempt work for Geneseo
Any structure over 120 sq ft, pools over 18" deep, generators, fences, structural work
- Exempt Sheds under 120 sq ft (zoning setbacks still apply)
- Exempt Cosmetic finishes
- Exempt Landscaping (non-structural)
Note: Exempt from building permit does not mean exempt from zoning and planning requirements. Confirm with the City of Geneseo Building Department before proceeding.
- Building Permit Application
- 2 sets of plans
- Site Plan
- Building code
- 2012 IBC/IRC (transitioning to 2021 per state law)
- Permit validity
- 1 year
- Owner-builder
- Allowed for primary residence
- Contractor requirements
- Mandatory registration for all contractors
Application process
Typical processing: 5-10 business days
- 01 Complete Building Permit Application
- 02 Submit with site plan and construction drawings
- 03 Review by Building Inspector
- 04 Approval and fee payment
Typical processing time: 5-10 business days
Fee schedule
Geneseo building permit fees
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- (309) 944-6419 (phone)
- Inspection hours
- 8:00 AM - 4:00 PM
Typical sequence: Typical sequence: Footing, Foundation, Rough-ins, Framing, Final
Frequently asked
Common questions about Geneseo permits
01 Do I need a building permit in Geneseo, IL? ▸
02 How much does a building permit cost in Geneseo, IL? ▸
03 How do I apply for a building permit in Geneseo, IL? ▸
04 How long does it take to get a building permit in Geneseo, IL? ▸
05 What work is exempt from building permits in Geneseo, IL? ▸
06 How do I schedule a building inspection in Geneseo, IL? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with City of Geneseo Building Department before applying. Jaspector is not legal advice.