jaspector
§ IL Bond County
City building permits

City of Greenville

How to apply for a building permit in City of Greenville, Illinois. Permit authority, application steps, fees, and inspection requirements.

Min. permit fee
$45.00
Last verified
April 2026
On this page 6
§ 01

Permit authority

City of Greenville Municipal Building

Street address
404 S. 3rd Street, Greenville, IL 62246
Coverage
Within the corporate limits of the City of Greenville.
§ 02

When a permit is required

Permit triggers and exempt work for Greenville

New construction, additions, alterations, repairs, or demolition.

One-story detached accessory structures under 200 square feet.
Fences not over 7 feet high.
Retaining walls under 4 feet high.
Cosmetic work (painting, tiling, carpeting, cabinets).
Sidewalks and driveways less than 30 inches above grade.
  • Exempt One-story detached accessory structures under 200 square feet.
  • Exempt Fences not over 7 feet high.
  • Exempt Retaining walls under 4 feet high.
  • Exempt Cosmetic work (painting, tiling, carpeting, cabinets).
  • Exempt Sidewalks and driveways less than 30 inches above grade.
Required documents
  • Completed application
  • Site plan
  • Construction drawings (structural, electrical, plumbing)
Building code
2021 International Building Code (IBC) and 2021 International Residential Code (IRC) as required by Illinois Public Act 103-0510 (effective January 1, 2025). Note: City was previously following 2015 IBC/IRC.
Owner-builder
Allowed for primary residence.
Contractor requirements
Contractors must be registered; plumbers and electricians must be state licensed.
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Obtain application from City Hall or City Clerk's office.
  2. 02
    Submit completed application with construction plans for review.
  3. 03
    Plans are reviewed for zoning and code compliance.
  4. 04
    Pay applicable permit fees.
  5. 05
    Permit is issued; construction may begin.

Source: City of Greenville Municipal Building ↗

§ 04

Fee schedule

Greenville building permit fees

Fee type
Amount
01
Minimum permit fee
$45.00
02
Plan check fee
$50 to $333+ based on project cost.
03
Permit fee formula
Valuation-based tiered schedule: $0–$2,000 = $45; $2,000–$3,000 = $50; higher valuations follow tiered formula.
04
Reinspection fee
$40.00 per visit for code violations.

Checks or cash at City Hall.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • 618-664-1644 (phone)
Inspection hours
Standard business hours.

Typical sequence: Typical sequence: footing/foundation, framing, rough-in (electric/plumbing), final.

§ 06

Frequently asked

Common questions about Greenville permits

01 Do I need a building permit in Greenville, IL?
New construction, additions, alterations, repairs, or demolition.
02 How much does a building permit cost in Greenville, IL?
Building permit fees in Greenville, IL are set by the local building department and vary by project type and valuation. The minimum permit fee is $45.00. Fees are calculated as: Valuation-based tiered schedule: $0–$2,000 = $45; $2,000–$3,000 = $50; higher valuations follow tiered formula.. Plan check fee: $50 to $333+ based on project cost..
03 How do I apply for a building permit in Greenville, IL?
To apply for a building permit in Greenville, IL, follow these steps: 1. Obtain application from City Hall or City Clerk's office. 2. Submit completed application with construction plans for review. 3. Plans are reviewed for zoning and code compliance. 4. Pay applicable permit fees. 5. Permit is issued; construction may begin.
04 What work is exempt from building permits in Greenville, IL?
Not all construction work requires a permit in Greenville, IL. The following work is generally exempt: One-story detached accessory structures under 200 square feet.; Fences not over 7 feet high.; Retaining walls under 4 feet high.; Cosmetic work (painting, tiling, carpeting, cabinets).; Sidewalks and driveways less than 30 inches above grade.. When in doubt, confirm with the local building department before starting work.
05 How do I schedule a building inspection in Greenville, IL?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Greenville, IL via: 618-664-1644.
last verified April 2026 source City of Greenville Municipal Building ↗ entry id permits/illinois/bond/greenville

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Greenville Municipal Building before applying. Jaspector is not legal advice.