§ 01

Permit authority

City of Wallace Planning & Zoning Department

Coverage
All properties within the City of Wallace. Wallace is the only city in the United States entirely listed in the National Historic Register (National Historic Landmark), requiring additional historic preservation review for all projects.
§ 02

When a permit is required

Permit triggers and exempt work for Wallace

Building permits required for new construction, additions, alterations, and structural changes. All projects require approval from Historic Preservation Commission to maintain historic character.

Note: Because Wallace is entirely listed on the National Historic Register, no exterior portion of any building, structure, fence, light fixture, steps, pavement, or utility structure can be erected, altered, restored, moved, or demolished without prior approval of a Certificate of Appropriateness.

Required documents
  • Clear statement of proposed work
  • Colors, materials, landscaping, and signs to be used
  • Plans, elevations, and specifications showing size, height, and completed appearance
  • Site plan showing existing buildings and proposed work
  • Additional information as required by Historic Preservation Commission application forms
Building code
Idaho Existing Building Code 2018; International Building Code (IBC) 2018 with Idaho amendments
Contractor requirements
Contractors must comply with historic building standards and use appropriate materials and methods approved by HPC.

Source: City of Wallace Planning & Zoning Department ↗

§ 03

Application process

Typical processing: 45 days for HPC hearing and decision; 1 week for building permit after HPC approval.

  1. 01
    Prepare project plans, elevations, specifications, site plan showing existing buildings and proposed work, and clear statement of proposed work.
  2. 02
    Include colors, materials, landscaping, and signs to be used in application materials.
  3. 03
    Submit Certificate of Appropriateness application to City of Wallace Planning & Zoning Department.
  4. 04
    Historic Preservation Commission reviews application; hearing held within 45 days of application receipt.
  5. 05
    HPC must approve project before building inspector can issue permit.
  6. 06
    Once HPC approves Certificate of Appropriateness, application goes to building inspector.
  7. 07
    Building permit typically issued within 1 week after HPC approval.

Typical processing time: 45 days for HPC hearing and decision; 1 week for building permit after HPC approval.

Source: City of Wallace Planning & Zoning Department ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • City of Wallace Planning & Zoning (phone)
§ 05

Frequently asked

Common questions about Wallace permits

01 Do I need a building permit in Wallace, ID?
Building permits required for new construction, additions, alterations, and structural changes. All projects require approval from Historic Preservation Commission to maintain historic character.
02 How do I apply for a building permit in Wallace, ID?
To apply for a building permit in Wallace, ID, follow these steps: 1. Prepare project plans, elevations, specifications, site plan showing existing buildings and proposed work, and clear statement of proposed work. 2. Include colors, materials, landscaping, and signs to be used in application materials. 3. Submit Certificate of Appropriateness application to City of Wallace Planning & Zoning Department. 4. Historic Preservation Commission reviews application; hearing held within 45 days of application receipt. 5. HPC must approve project before building inspector can issue permit. 6. Once HPC approves Certificate of Appropriateness, application goes to building inspector. 7. Building permit typically issued within 1 week after HPC approval.
03 How long does it take to get a building permit in Wallace, ID?
Building permit processing times in Wallace, ID typically run 45 days for HPC hearing and decision; 1 week for building permit after HPC approval.. Timelines can vary based on project complexity and current department workload.
04 How do I schedule a building inspection in Wallace, ID?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Wallace, ID via: City of Wallace Planning & Zoning.
last verified April 2026 source City of Wallace Planning & Zoning Department ↗ entry id permits/idaho/shoshone/wallace

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Wallace Planning & Zoning Department before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Shoshone County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Shoshone County jurisdictions →