§ 01

Permit authority

Teton County Building Department

Street address
150 Courthouse Drive - Room 107, Driggs, ID 83422
Coverage
City of Teton is shared between Madison County and Teton County; Teton County Building Department handles most permit matters.
§ 02

When a permit is required

Permit triggers and exempt work for Teton (Madison County Portion)

A building permit is required for construction within the City of Teton.

Required documents
  • Completed permit application
  • Construction plans
  • Site plan
Building code
2018 International Building Codes (I-Codes) with Flood Control Ordinance compliance required
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    Contact Teton County Building Department for permit requirements.
  2. 02
    Prepare building permit application and plans.
  3. 03
    Submit application with required documentation.
  4. 04
    County staff reviews application for completeness and code compliance.
  5. 05
    Ensure compliance with Flood Control Ordinance as applicable.
  6. 06
    Pay permit fees and obtain building permit.
  7. 07
    Schedule required inspections.
  8. 08
    Complete construction and final inspection.

Source: Teton County Building Department ↗

§ 04

Required inspections

Scheduling and sequence

Inspection hours
Monday–Thursday 9:00 am–5:00 pm; Friday 9:00 am–Noon
§ 05

Frequently asked

Common questions about Teton (Madison County Portion) permits

01 Do I need a building permit in Teton (Madison County Portion), ID?
A building permit is required for construction within the City of Teton.
02 How do I apply for a building permit in Teton (Madison County Portion), ID?
To apply for a building permit in Teton (Madison County Portion), ID, follow these steps: 1. Contact Teton County Building Department for permit requirements. 2. Prepare building permit application and plans. 3. Submit application with required documentation. 4. County staff reviews application for completeness and code compliance. 5. Ensure compliance with Flood Control Ordinance as applicable. 6. Pay permit fees and obtain building permit. 7. Schedule required inspections. 8. Complete construction and final inspection.
last verified April 2026 source Teton County Building Department ↗ entry id permits/idaho/madison/teton

Educational reference. Permit rules and fees change — confirm current requirements directly with Teton County Building Department before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Madison County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Madison County jurisdictions →