§ 01

Permit authority

Tift County Community Development Services

Street address
225 Tift Avenue, Building D, Tifton, GA 31794
Coverage
Tift County Community Development Services performs permitting, building inspections and plan review, and code enforcement for the City of Ty Ty. Ty Ty City Hall remains the municipal government contact, but public permit routing is through the county office.
§ 02

When a permit is required

Permit triggers and exempt work for Ty Ty

Public Ty Ty permit materials route through Tift County Community Development Services for building permits, plan review, and inspections. The reviewed public record did not include a Ty Ty-specific exempt-work sheet.

Note: No public exempt-work list for Ty Ty building permits was found in the reviewed materials.

Required documents
  • Owner authorization (if needed)
  • Plat and/or deed
  • Site plan with setbacks
  • Construction details and plans
  • Contractor names and license information
  • Septic or utility approval
  • 911 address request
  • Driveway application (if applicable)
  • Other project-specific items
Building code
Ty Ty public permit administration runs through Tift County, whose UDC adopts the Georgia-amended ICC and NEC code set by reference, including future editions and DCA amendments.
Permit validity
No public Ty Ty-specific building permit expiration rule located. Land disturbance permit expiration follows the county UDC.
Owner-builder
No public Ty Ty-specific owner-builder rule located in the reviewed materials. Georgia state owner-builder rule in O.C.G.A. 43-41-17(h) applies where a local permit is required.
Contractor requirements
County checklist says contractors need to be licensed, and if located in city the contractor business license copy is also needed. Mobile homes require a state licensed installer and electrician.
§ 03

Application process

Typical processing: No public general building-permit turnaround located. City-located projects are reviewed on Fridays per the county checklist. Land disturbance permits are subject to the UDC 45-calendar-day review cap for completed applications.

  1. 01
    Start with Tift County Community Development Services, which the county states handles permitting and inspections for Ty Ty
  2. 02
    Assemble the posted county checklist materials that apply to the project: plat and/or deed, site plan with setbacks, plans, contractor information, septic or utility approvals, driveway form, and other scope-specific items
  3. 03
    For projects in city limits, the county building checklist states city-located projects go before City Permit Review every Friday; minor-project information is needed before noon on Thursday, with other items moving to the next Friday committee review
  4. 04
    County staff reviews the application and supporting materials for compliance with the UDC and applicable codes
  5. 05
    After permit issuance, request inspections by phone at least 24 hours in advance
  6. 06
    Obtain certificate of occupancy or completion before occupancy or use where required

Typical processing time: No public general building-permit turnaround located. City-located projects are reviewed on Fridays per the county checklist. Land disturbance permits are subject to the UDC 45-calendar-day review cap for completed applications.

Source: Tift County Community Development Services ↗

§ 04

Fee schedule

Ty Ty building permit fees

Fee type
Amount
01
Permit fee formula
Not publicly posted for ordinary building permits. County UDC land disturbance fees apply where applicable ($40 per acre or fraction).

UDC states applications are not complete until required fees are paid, but no Ty Ty building-fee schedule was found in public materials reviewed.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • Call Tift County Community Development Services at (229) 386-7961 (phone)
Scheduling deadline
24 hours advance notice required per county checklist
Inspection hours
Monday-Friday, 8:00 am to 5:00 pm

Typical sequence: No public Ty Ty inspection sequence handout found. Final certificate of occupancy or completion is required before occupancy or use where applicable.

Source: Tift County Community Development Services ↗

§ 06

Frequently asked

Common questions about Ty Ty permits

01 Do I need a building permit in Ty Ty, GA?
Public Ty Ty permit materials route through Tift County Community Development Services for building permits, plan review, and inspections. The reviewed public record did not include a Ty Ty-specific exempt-work sheet.
02 How much does a building permit cost in Ty Ty, GA?
Building permit fees in Ty Ty, GA are set by the local building department and vary by project type and valuation. Fees are calculated as: Not publicly posted for ordinary building permits. County UDC land disturbance fees apply where applicable ($40 per acre or fraction)..
03 How do I apply for a building permit in Ty Ty, GA?
To apply for a building permit in Ty Ty, GA, follow these steps: 1. Start with Tift County Community Development Services, which the county states handles permitting and inspections for Ty Ty 2. Assemble the posted county checklist materials that apply to the project: plat and/or deed, site plan with setbacks, plans, contractor information, septic or utility approvals, driveway form, and other scope-specific items 3. For projects in city limits, the county building checklist states city-located projects go before City Permit Review every Friday; minor-project information is needed before noon on Thursday, with other items moving to the next Friday committee review 4. County staff reviews the application and supporting materials for compliance with the UDC and applicable codes 5. After permit issuance, request inspections by phone at least 24 hours in advance 6. Obtain certificate of occupancy or completion before occupancy or use where required
04 How long does it take to get a building permit in Ty Ty, GA?
Building permit processing times in Ty Ty, GA typically run No public general building-permit turnaround located. City-located projects are reviewed on Fridays per the county checklist. Land disturbance permits are subject to the UDC 45-calendar-day review cap for completed applications.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Ty Ty, GA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Ty Ty, GA via: Call Tift County Community Development Services at (229) 386-7961. 24 hours advance notice required per county checklist.
last verified April 2026 source Tift County Community Development Services ↗ entry id permits/georgia/tift/ty-ty

Educational reference. Permit rules and fees change — confirm current requirements directly with Tift County Community Development Services before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Tift County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Tift County jurisdictions →