On this page 6
When a permit is required
Permit triggers and exempt work for Hamilton
New residential construction, additions, accessory structures above county exemption thresholds, decks meeting permit thresholds, remodels, pools, demolitions, manufactured housing, and separate trade work as applicable
- Exempt Detached accessory buildings 400 square feet or less when meeting all county criteria (no human habitation, no toilet facilities, one story max, no more than 100-amp electrical service)
- Exempt Buildings 400 square feet or less if no electricity
- Exempt Agricultural buildings over 800 square feet require permit; 800 square feet or less exempt if otherwise qualifying
- Exempt Decks under 30 inches above grade or 100 square feet or less in area
Note: No broader county public exempt-work list was found
- Recorded plat or substitute deed/tax map
- Two site plans
- Complete plans (two sets)
- Driveway permit
- Sewage management application where applicable
- Erosion documents where applicable
- Contractor license or business license information
- Building code
- Georgia state minimum standard construction codes enforced locally by Harris County. 2018 International Swimming Pool and Spa Code with 2018 Georgia amendments and 2023 National Electrical Code for pool-related work.
- Owner-builder
- Homeowner building their own home and personally doing all electrical, plumbing, and mechanical work may pull those permits; otherwise trade permits must be pulled by Georgia licensed contractors
- Contractor requirements
- Residential work over $2,500 requires Georgia residential contractor licensure under O.C.G.A. 43-41; current occupation tax certificate or business license required. Trade permits must be pulled by Georgia licensed electrician, plumber, or HVAC contractor unless owner-builder exception applies.
Application process
Application → plan check → issuance → inspection → final
- 01 Confirm zoning and site constraints with Harris County Community Development
- 02 Gather prerequisite documents from the county permit packet including driveway permit, on-site sewage management application where applicable, recorded plat or deed/tax map, two site plans, NOI/EPD erosion documents where applicable, and two sets of complete plans
- 03 Bring contractor information or homeowner information
- 04 Submit through Harris County Community Development in-office
- 05 Pull separate trade permits as needed (electrical, plumbing, mechanical) by Georgia licensed contractors, except owner-builder exception
- 06 Pay fees after staff review and permit calculation
- 07 Schedule and pass required inspections for final approval
Fee schedule
Hamilton building permit fees
Credit card convenience fee is $3 minimum for first $100 or 3 percent if over $100. Email: hcpermits@harriscountyga.gov or fax: 706-628-4140
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- Phone/email/in-office coordination with Harris County Community Development (phone)
- Inspection hours
- Monday through Friday, 8:00 a.m. to 5:00 p.m.
Typical sequence: Varies by permit type. Pool inspections: electrical grounding/bonding first, then pool final. Standard vertical construction sequence not consolidated in public sources.
Frequently asked
Common questions about Hamilton permits
01 Do I need a building permit in Hamilton, GA? ▸
02 How much does a building permit cost in Hamilton, GA? ▸
03 How do I apply for a building permit in Hamilton, GA? ▸
04 What work is exempt from building permits in Hamilton, GA? ▸
05 How do I schedule a building inspection in Hamilton, GA? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Harris County Community Development before applying. Jaspector is not legal advice.