How to apply for a building permit in City of St. Marks, Florida. Permit authority, application steps, fees, and inspection requirements.

Code adoption
Wakulla County Building Code
Last verified
April 2026
On this page 6
§ 01

Permit authority

City of St. Marks Building and Zoning

Street address
32 Shell Island Rd, St. Marks, FL 32355
Coverage
City of St. Marks. The city requires site plan approval before applicants submit permits to Wakulla County. The city has adopted the Wakulla County Building Code.
Online portal
City of St. Marks Permits
Manual submission
§ 02

When a permit is required

Permit triggers and exempt work for St. Marks

Property owners must obtain city site plan approval for improvements before submitting to the county for permit issuance.

AC changeout
Fill dirt
Fences
Reroofs
  • Exempt AC changeout
  • Exempt Fill dirt
  • Exempt Fences
  • Exempt Reroofs

Note: The city states that simple projects may not require a Local Planning Board meeting, but this does not mean they are exempt from city review or county permitting. Applicants must still obtain the required city approval letter and county permit determination.

Required documents
  • Completed application
  • Property owner's original signature
  • Digital copy of site plan
  • Two physical copies of site plan
  • Deed and legal description
  • Stormwater certification
  • Transportation concurrency review application
  • Additional items may be required: wetland delineations, traffic studies, or drainage reports depending on project type and location
Building code
Wakulla County Building Code
Permit validity
Not clearly identified from reviewed city pages.
Owner-builder
Not identified from St. Marks public pages. County owner-builder rules apply once permit moves to Wakulla County.
Contractor requirements
Not clearly published by the city. County contractor registration requirements apply for the county-issued permit.

Source: City of St. Marks Building and Zoning ↗

§ 03

Application process

Typical processing: Site plan packages not requiring a Local Planning Board meeting typically take 2-4 business days if no additional administrative work is needed. Projects requiring a Local Planning Board meeting must be submitted at least 10 days before the meeting.

  1. 01
    Prepare a completed city site plan application package with the property owner's original signature.
  2. 02
    Include required materials: digital copy of site plan, completed application, deed and legal description, stormwater certification, transportation concurrency review application, two physical copies of site plan, and fees.
  3. 03
    For simple projects (AC changeout, fill dirt, fences, reroofs), a Local Planning Board meeting is not required unless the City Manager or City Attorney determines otherwise.
  4. 04
    For projects requiring a Local Planning Board meeting, submit the package at least 10 days before the meeting date.
  5. 05
    After receiving the city approval letter, submit the building permit to Wakulla County for final permit issuance and county inspection processing.

Typical processing time: Site plan packages not requiring a Local Planning Board meeting typically take 2-4 business days if no additional administrative work is needed. Projects requiring a Local Planning Board meeting must be submitted at least 10 days before the meeting.

Source: City of St. Marks Building and Zoning ↗

§ 04

Fee schedule

St. Marks building permit fees

Fee type
Amount
01
Minimum permit fee
Not clearly confirmed. The city references Resolution 2025-05 Building Permit Fees, but public link currently resolves to site plan application PDF.
02
Plan check fee
Not clearly confirmed.
03
Permit fee formula
Not clearly confirmed from public materials reviewed.

City fees apply to the city site plan approval layer. County permit fees still apply once the permit moves to Wakulla County.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

Inspection hours
Monday through Friday, 8:00 a.m. to 4:00 p.m.

Typical sequence: The city performs front-end site plan and zoning/flood review. Permit then proceeds to Wakulla County for permit issuance and county inspections.

Source: City of St. Marks Building and Zoning ↗

§ 06

Frequently asked

Common questions about St. Marks permits

01 Do I need a building permit in St. Marks, FL?
Property owners must obtain city site plan approval for improvements before submitting to the county for permit issuance.
02 How much does a building permit cost in St. Marks, FL?
Building permit fees in St. Marks, FL are set by the local building department and vary by project type and valuation. The minimum permit fee is Not clearly confirmed. The city references Resolution 2025-05 Building Permit Fees, but public link currently resolves to site plan application PDF.. Fees are calculated as: Not clearly confirmed from public materials reviewed.. Plan check fee: Not clearly confirmed..
03 How do I apply for a building permit in St. Marks, FL?
To apply for a building permit in St. Marks, FL, follow these steps: 1. Prepare a completed city site plan application package with the property owner's original signature. 2. Include required materials: digital copy of site plan, completed application, deed and legal description, stormwater certification, transportation concurrency review application, two physical copies of site plan, and fees. 3. For simple projects (AC changeout, fill dirt, fences, reroofs), a Local Planning Board meeting is not required unless the City Manager or City Attorney determines otherwise. 4. For projects requiring a Local Planning Board meeting, submit the package at least 10 days before the meeting date. 5. After receiving the city approval letter, submit the building permit to Wakulla County for final permit issuance and county inspection processing.
04 How long does it take to get a building permit in St. Marks, FL?
Building permit processing times in St. Marks, FL typically run Site plan packages not requiring a Local Planning Board meeting typically take 2-4 business days if no additional administrative work is needed. Projects requiring a Local Planning Board meeting must be submitted at least 10 days before the meeting.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in St. Marks, FL?
Not all construction work requires a permit in St. Marks, FL. The following work is generally exempt: AC changeout; Fill dirt; Fences; Reroofs. Note: The city states that simple projects may not require a Local Planning Board meeting, but this does not mean they are exempt from city review or county permitting. Applicants must still obtain the required city approval letter and county permit determination. When in doubt, confirm with the local building department before starting work.
last verified April 2026 source City of St. Marks Building and Zoning ↗ entry id permits/florida/wakulla/st-marks

Educational reference. Permit rules and fees change — confirm current requirements directly with City of St. Marks Building and Zoning before applying. Jaspector is not legal advice.