jaspector
City building permits

Town of Mayo

How to apply for a building permit in Town of Mayo, Florida. Permit authority, application steps, fees, and inspection requirements.

Code adoption
2023 Florida Building Code, 8th Edition
Min. permit fee
$125
Last verified
April 2026
On this page 6
§ 01

Permit authority

Lafayette County Building Department (serving Town of Mayo)

Street address
120 W. Main Street, Mayo, FL 32066
Coverage
All properties within the incorporated Town of Mayo limits.
Online portal
Building Department Online Submission
County web submission
§ 02

When a permit is required

Permit triggers and exempt work for Mayo

A building permit is required for most construction in the Town of Mayo.

Note: No Town of Mayo-specific exemption list was located. Applicants should confirm exemption questions with the Lafayette County Building Department before starting work.

Required documents
  • Completed permit application
  • Workers' compensation certificate or exemption
  • Copy of state contractor license
  • Copy of business tax receipt
  • Subcontractor list with trades if applicable
  • Health Department permit for septic if applicable
  • Site plan or current survey
  • Two sets of sealed drawings
  • One set of sealed truss drawings
  • Energy calculations
  • Manual J HVAC load calculations
  • Copy of recorded Notice of Commencement
  • Product approval sheet
Building code
2023 Florida Building Code, 8th Edition
Permit validity
Contact the Building Department for current permit validity periods.
Owner-builder
Owners must personally appear to sign if pulling the permit under an exemption and must directly supervise the work within Florida owner-builder limits.
Contractor requirements
Contractors must hold valid state licenses, workers' compensation insurance, and current business tax receipt.

Source: Lafayette County Building Department (serving Town of Mayo) ↗

§ 03

Application process

Typical processing: Processing times vary by project type and completeness; contact the Building Department for estimate.

  1. 01
    Confirm the parcel is inside the Town of Mayo.
  2. 02
    Use the Lafayette County Building Department form set for the permit type.
  3. 03
    Submit through the county Building Department's online submission page or email.
  4. 04
    Provide all required county supporting materials, including plans, site-plan, septic documentation, product approvals, and Notice of Commencement items applicable to the project type.
  5. 05
    Confirm with Town Hall whether any separate local business license, utility, or municipal administrative step applies.
  6. 06
    Complete county-administered inspections and final approval before occupancy.

Typical processing time: Processing times vary by project type and completeness; contact the Building Department for estimate.

Source: Lafayette County Building Department (serving Town of Mayo) ↗

§ 04

Fee schedule

Effective October 1, 2025

Fee type
Amount
01
Minimum permit fee
$125
02
Plan check fee
Included in permit fee
03
Permit fee formula
Residential conditioned space: $0.50/sq ft; Residential unconditioned space: $0.40/sq ft; Commercial conditioned space: $0.60/sq ft; Commercial unconditioned space: $0.50/sq ft
04
Trade permit fee
$125 for electrical, plumbing, HVAC, roof, gas, floating docks, demolition, residential re-roof, agricultural poles, electrical upgrades, and electrical 200 amps base
05
Reinspection fee
$40

DocuSign fee: $20. Impact fee: $412.50 effective October 1, 2025 for all new dwelling units including RVs. Confirm any separate town-side fee with Town Hall before filing.

Fees change periodically. Confirm at the official fee schedule ↗ (effective October 1, 2025) before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • 386-294-3611 (phone)
  • buildingdept@lafayettecountyfl.org (email)
Inspection hours
Monday through Friday, 8:00 AM to 5:00 PM

Typical sequence: Inspections are administered by the shared Building Official through the county process.

Source: Lafayette County Building Department (serving Town of Mayo) ↗

§ 06

Frequently asked

Common questions about Mayo permits

01 Do I need a building permit in Mayo, FL?
A building permit is required for most construction in the Town of Mayo.
02 How much does a building permit cost in Mayo, FL?
Building permit fees in Mayo, FL are set by the local building department and vary by project type and valuation. The minimum permit fee is $125. Fees are calculated as: Residential conditioned space: $0.50/sq ft; Residential unconditioned space: $0.40/sq ft; Commercial conditioned space: $0.60/sq ft; Commercial unconditioned space: $0.50/sq ft. Plan check fee: Included in permit fee.
03 How do I apply for a building permit in Mayo, FL?
To apply for a building permit in Mayo, FL, follow these steps: 1. Confirm the parcel is inside the Town of Mayo. 2. Use the Lafayette County Building Department form set for the permit type. 3. Submit through the county Building Department's online submission page or email. 4. Provide all required county supporting materials, including plans, site-plan, septic documentation, product approvals, and Notice of Commencement items applicable to the project type. 5. Confirm with Town Hall whether any separate local business license, utility, or municipal administrative step applies. 6. Complete county-administered inspections and final approval before occupancy.
04 How long does it take to get a building permit in Mayo, FL?
Building permit processing times in Mayo, FL typically run Processing times vary by project type and completeness; contact the Building Department for estimate.. Timelines can vary based on project complexity and current department workload.
05 How do I schedule a building inspection in Mayo, FL?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Mayo, FL via: 386-294-3611, buildingdept@lafayettecountyfl.org.
last verified April 2026 source Lafayette County Building Department (serving Town of Mayo) ↗ entry id permits/florida/lafayette/mayo

Educational reference. Permit rules and fees change — confirm current requirements directly with Lafayette County Building Department (serving Town of Mayo) before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Lafayette County.

Same county, different permit office. Click for that jurisdiction's full guide.

All Lafayette County jurisdictions →