When a permit is required
Permit triggers and exempt work for Georgetown
All construction, alterations, additions, demolitions, and similar work within town limits.
Note: Not enumerated on public pages; contact town planning department.
- Completed application
- Construction plans conforming to town ordinances and applicable laws
- Fee payment
- Building code
- Sussex County adopted codes (2021 IBC, 2021 IRC) plus town zoning ordinances. Town Zoning Code at https://ecode360.com/6476908.
- Permit validity
- Permit becomes null and void if construction is not substantially commenced within 90 days of issuance.
- Owner-builder
- Not detailed on public pages; contact town.
- Contractor requirements
- State of Delaware contractor license required; contact town for local requirements.
Source: Town of Georgetown Community Development / Planning Department ↗
Application process
Typical processing: Up to 20 working days for Town Council approval; zoning-compliant projects approximately 3 weeks.
- 01 Download building permit application from the town website or pick up at Town Hall.
- 02 Complete application with all required information and plans.
- 03 Submit application with construction plans and required documents to Town Planning Department.
- 04 Town Council approves or rejects applications within 20 working days of a completed submission.
- 05 Projects in complete compliance with Town Zoning Code are administratively approved; all town reviews completed within approximately 3 weeks.
- 06 Town building permit is issued.
- 07 Apply separately to Sussex County for county building permit at 2 The Circle, Georgetown.
- 08 Post permits on job site and proceed with construction.
- 09 Permit becomes null and void if construction is not substantially commenced within 90 days of issuance.
Typical processing time: Up to 20 working days for Town Council approval; zoning-compliant projects approximately 3 weeks.
Source: Town of Georgetown Community Development / Planning Department ↗
Fee schedule
Georgetown building permit fees
Payment at Town Hall.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- Contact Town Planning Department via website (in-person)
Typical sequence: Not enumerated publicly; Sussex County Building Code Office may conduct inspections.
Source: Town of Georgetown Community Development / Planning Department ↗
Frequently asked
Common questions about Georgetown permits
01 Do I need a building permit in Georgetown, DE? ▸
02 How much does a building permit cost in Georgetown, DE? ▸
03 How do I apply for a building permit in Georgetown, DE? ▸
04 How long does it take to get a building permit in Georgetown, DE? ▸
05 How do I schedule a building inspection in Georgetown, DE? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Town of Georgetown Community Development / Planning Department before applying. Jaspector is not legal advice.