When a permit is required
Permit triggers and exempt work for Las Animas
The permit application requires a permit for new buildings, structures, additions, remodeling, and alterations to existing buildings. The form also requires a site inspection before construction begins.
Note: The city documents and permit application reviewed did not publish a standalone exempt-work list.
- Application form
- Plans and drawings when applicable
- Setbacks shown on drawings
- Plans, specifications, engineering calculations, diagrams, soil investigation reports, special inspection and structural observation documents when needed
- Permit validity
- A permit expires if work is not commenced within 180 days from the permit date or if work is suspended or abandoned for 180 days. One extension of up to 180 days may be granted on written request if circumstances beyond the permittee's control prevented action.
- Contractor requirements
- The application requests contractor, engineer, and architect information. When documents must be prepared by a licensed architect or engineer, the city may require an architect or engineer of record.
Application process
Application → plan check → issuance → inspection → final
- 01 Download or obtain the City of Las Animas Building Permit Application from the city documents page.
- 02 Complete the application with project description, intended use, total project cost, debris disposal location, and plans or drawings when applicable.
- 03 Submit plans and supporting documents for city review.
- 04 City staff review the application and plans for code conformity and fee payment.
- 05 Site inspection occurs before construction begins, per the permit notice.
- 06 Permit is issued after review and payment if the work complies.
Fee schedule
Las Animas building permit fees
The form states that building or construction materials purchased outside City limits and Bent County are subject to a 5 percent use/sales tax. It also states that a prepayment based on 50 percent of project cost as materials may be required at application, with reconciliation after completion.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- (719) 456-2571 (phone)
- Scheduling deadline
- 24 hours advance notice must be given before a building inspection can be scheduled.
Typical sequence: The permit notice states the building permit must be obtained and the site inspected by the city building inspector before construction begins. Special inspections and structural observation, when required, must be approved as part of the permit process.
Frequently asked
Common questions about Las Animas permits
01 Do I need a building permit in Las Animas, CO? ▸
02 How much does a building permit cost in Las Animas, CO? ▸
03 How do I apply for a building permit in Las Animas, CO? ▸
04 How do I schedule a building inspection in Las Animas, CO? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with City Clerk and Building Inspector function before applying. Jaspector is not legal advice.