§ CA Marin County
City building permits

City of Belvedere

How to apply for a building permit in City of Belvedere, California. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

City of Belvedere Planning & Building Department

Street address
450 San Rafael Avenue, Belvedere, CA 94920
Coverage
Applies within the incorporated City of Belvedere, Marin County. Separate outside-agency approvals may also be required for fire, sewer, water, and right-of-way work.
Online portal
iWorQ
iWorQ
§ 02

When a permit is required

Permit triggers and exempt work for Belvedere

Belvedere requires building permits for all additions, alterations, repairs, and all maintenance to electrical, plumbing, and mechanical systems. Most exterior changes also require Planning Design Review even if a building permit is exempt.

Painting, wallpapering, bookshelves, cabinets, tile, or marble work
Fences and gates not higher than 6 feet
Roof, deck, and siding repairs of 100 square feet or less
Retaining walls less than 4 feet high where there is no lateral pressure against the wall
  • Exempt Painting, wallpapering, bookshelves, cabinets, tile, or marble work
  • Exempt Fences and gates not higher than 6 feet
  • Exempt Roof, deck, and siding repairs of 100 square feet or less
  • Exempt Retaining walls less than 4 feet high where there is no lateral pressure against the wall

Note: Belvedere says these exemptions apply only when the work is a single activity or not part of a larger project. The city also states that most exterior changes still require Planning Design Review even when a building permit is exempt.

Required documents
  • Building Permit Application
  • plans sized and counted per project type
  • for larger projects, drainage plan, erosion plan, landscape plan, specifications, engineering calculations, energy calculations, geotechnical reports, and special inspection / structural observation programs
  • final construction cost evaluation statement at project completion
  • outside-agency approvals when applicable
Building code
Belvedere's public FAQ page still lists older 2016 California codes, but the city's Recent City Ordinances page shows Ordinance 2025-09: CA Building Standards Codes. Based on that newer ordinance listing, the city has updated construction code adoption beyond the stale FAQ entry; confirm the exact currently adopted edition and local amendments directly from Ordinance 2025-09 before relying on it for permit documents.
Permit validity
Belvedere materials state building permits are valid for 180 days from permit issuance, and each inspection resets that 180-day clock. Separately, the city's Construction Time Limit rules assign overall project completion windows of 6, 12, 18, or 24 months based on valuation, with extensions required if work is not completed in time.
Owner-builder
Belvedere uses an Owner-Builder Acknowledgement form. The property owner must read, initial, sign, and return it before permit issuance for owner-builder permits. An agent cannot execute the notice without prior approval of the permitting authority. The form warns of liability, employer obligations, and resale limits under California owner-builder law.
Contractor requirements
Belvedere's owner-builder form states California contractors must be licensed and bonded and must list their license numbers on permits and contracts. Belvedere's contractor guidelines also state all general and subcontractors must have a current City business license.
§ 03

Application process

Typical processing: Expedited staff review about 1 to 2 days for small projects; standard staff review about +/- 10 days for medium projects; larger projects receive an initial plan review letter in about +/- 30 days or about 28 working days for larger complex applications.

  1. 01
    Confirm whether the work needs a building permit and whether Planning Design Review is also required. Belvedere states permits are required for all additions, alterations, repairs, and all electrical, plumbing, and mechanical maintenance; even when a building permit is exempt, most exterior changes still require Planning Design Review.
  2. 02
    Assemble the application package. Belvedere accepts digital submittals and prefers them by email. Depending on project size, applicants may need 4, 5, or 7 paper plan sets if filing in person. New structures, additions, and substantial remodels also need drainage, erosion, and landscape plans plus supporting documents such as specifications, engineering calculations, energy calculations, geotechnical reports, and special inspection / structural observation programs.
  3. 03
    Email the application and plans to the city staff listed by Belvedere for permit intake: Permit Technician Nancy Miller at nmiller@cityofbelvedere.org, Building Official Brian Van Son at bvanson@cityofbelvedere.org, and/or Associate Planner Samie Malakiman at smalakiman@cityofbelvedere.org. In-person submittal is also allowed at City Hall.
  4. 04
    Pay plan check fees at submittal. Belvedere's fee schedule says plan check fees are due when the application is submitted and are separate from permit issuance fees.
  5. 05
    Respond to review comments and obtain any required outside-agency approvals. Belvedere notes larger projects may require Engineering, Fire, and Public Works review before permit issuance.
  6. 06
    After permit issuance, schedule inspections by phone at (415) 435-8915. Requests made by 11:59 p.m. the day before are scheduled for the next inspection day.
  7. 07
    Complete all required finals and close-out items. Belvedere requires a final construction cost evaluation at project completion, and final approval may also depend on Tiburon Fire Protection District, Marin County Sanitary District No. 5, and Planning sign-off, depending on the project.
  8. 08
    If the project will run past the assigned construction time limit, apply for an extension before the permit expires and pay the applicable reactivation/extension fees.

Typical processing time: Expedited staff review about 1 to 2 days for small projects; standard staff review about +/- 10 days for medium projects; larger projects receive an initial plan review letter in about +/- 30 days or about 28 working days for larger complex applications.

Source: City of Belvedere Planning & Building Department ↗

§ 04

Fee schedule

Belvedere building permit fees

Fee type
Amount
01
Minimum permit fee
$171.75 for valuation from $1 to $2,000 under the base building permit schedule; many stand-alone trade permits start at $95
02
Plan check fee
Building plan review fee is 75% of the permit fee if applicable; planning and engineering building plan check fees are each the greater of $115 or 10% of the building permit fee when review is required
03
Permit fee formula
Base building permit fees are valuation-based for new buildings, additions, tenant improvements, residential remodels, and other permits not separately listed; separate flat fees apply to many stand-alone plumbing, mechanical, and electrical permits
04
Trade permit fee
$171.75 for valuation from $1 to $2,000 under the base building permit schedule; many stand-alone trade permits start at $95
05
Reinspection fee
Hourly rate for inspections, plan reviews, and re-inspections not otherwise listed is $229 per hour; after-hours inspection is $275 per hour with a 4-hour minimum
06
Penalty (no permit)
retroactive plumbing, mechanical, and electrical permits can be charged up to 5x the total permit cost; construction time limit extensions are 1x the original building permit fee for a first extension, 3x for a second extension, and up to 5x with City Council approval for a third extension

Plan check fees are due at application submittal. Belvedere also requires permit valuation at application and a final construction cost evaluation at close-out, which the city uses to compute final permit fees.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
Scheduling deadline
Inspections are conducted Monday through Thursday, generally 8:00 a.m. to 3:00 p.m. Requests received by 11:59 p.m. the day before are scheduled for the next inspection day. If a callback number is left, the inspector may provide a two-hour inspection window on the inspection day.
Inspection hours
Inspections are conducted Monday through Thursday, generally 8:00 a.m. to 3:00 p.m. Requests received by 11:59 p.m. the day before are scheduled for the next inspection day. If a callback number is left, the inspector may provide a two-hour inspection window on the inspection day.
Time windows
Inspections are conducted Monday through Thursday, generally 8:00 a.m. to 3:00 p.m. Requests received by 11:59 p.m. the day before are scheduled for the next inspection day. If a callback number is left, the inspector may provide a two-hour inspection window on the inspection day.

Typical sequence: Varies by project, but Belvedere materials specifically mention survey verification before foundation inspection where setbacks apply; Tiburon Fire sprinkler approval before framing inspection when required; building height survey verification at roof framing/sheathing for additions, new structures, and reconstructed roofs; then final approvals from Building and, where applicable, Planning, Tiburon Fire, and Marin County Sanitary District No. 5. Reinspection note: The fee schedule sets a $229 hourly rate for inspections, plan reviews, and re-inspections not otherwise listed. Failed or incomplete inspections can therefore lead to additional hourly charges.

Source: City of Belvedere Planning & Building Department ↗

§ 06

Frequently asked

Common questions about Belvedere permits

01 Do I need a building permit in Belvedere, CA?
Belvedere requires building permits for all additions, alterations, repairs, and all maintenance to electrical, plumbing, and mechanical systems. Most exterior changes also require Planning Design Review even if a building permit is exempt.
02 How much does a building permit cost in Belvedere, CA?
Building permit fees in Belvedere, CA are set by the local building department and vary by project type and valuation. The minimum permit fee is $171.75 for valuation from $1 to $2,000 under the base building permit schedule; many stand-alone trade permits start at $95. Fees are calculated as: Base building permit fees are valuation-based for new buildings, additions, tenant improvements, residential remodels, and other permits not separately listed; separate flat fees apply to many stand-alone plumbing, mechanical, and electrical permits. Plan check fee: Building plan review fee is 75% of the permit fee if applicable; planning and engineering building plan check fees are each the greater of $115 or 10% of the building permit fee when review is required.
03 How do I apply for a building permit in Belvedere, CA?
To apply for a building permit in Belvedere, CA, follow these steps: 1. Confirm whether the work needs a building permit and whether Planning Design Review is also required. Belvedere states permits are required for all additions, alterations, repairs, and all electrical, plumbing, and mechanical maintenance; even when a building permit is exempt, most exterior changes still require Planning Design Review. 2. Assemble the application package. Belvedere accepts digital submittals and prefers them by email. Depending on project size, applicants may need 4, 5, or 7 paper plan sets if filing in person. New structures, additions, and substantial remodels also need drainage, erosion, and landscape plans plus supporting documents such as specifications, engineering calculations, energy calculations, geotechnical reports, and special inspection / structural observation programs. 3. Email the application and plans to the city staff listed by Belvedere for permit intake: Permit Technician Nancy Miller at nmiller@cityofbelvedere.org, Building Official Brian Van Son at bvanson@cityofbelvedere.org, and/or Associate Planner Samie Malakiman at smalakiman@cityofbelvedere.org. In-person submittal is also allowed at City Hall. 4. Pay plan check fees at submittal. Belvedere's fee schedule says plan check fees are due when the application is submitted and are separate from permit issuance fees. 5. Respond to review comments and obtain any required outside-agency approvals. Belvedere notes larger projects may require Engineering, Fire, and Public Works review before permit issuance. 6. After permit issuance, schedule inspections by phone at (415) 435-8915. Requests made by 11:59 p.m. the day before are scheduled for the next inspection day. 7. Complete all required finals and close-out items. Belvedere requires a final construction cost evaluation at project completion, and final approval may also depend on Tiburon Fire Protection District, Marin County Sanitary District No. 5, and Planning sign-off, depending on the project. 8. If the project will run past the assigned construction time limit, apply for an extension before the permit expires and pay the applicable reactivation/extension fees.
04 How long does it take to get a building permit in Belvedere, CA?
Building permit processing times in Belvedere, CA typically run Expedited staff review about 1 to 2 days for small projects; standard staff review about +/- 10 days for medium projects; larger projects receive an initial plan review letter in about +/- 30 days or about 28 working days for larger complex applications.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in Belvedere, CA?
Not all construction work requires a permit in Belvedere, CA. The following work is generally exempt: Painting, wallpapering, bookshelves, cabinets, tile, or marble work; Fences and gates not higher than 6 feet; Roof, deck, and siding repairs of 100 square feet or less; Retaining walls less than 4 feet high where there is no lateral pressure against the wall. Note: Belvedere says these exemptions apply only when the work is a single activity or not part of a larger project. The city also states that most exterior changes still require Planning Design Review even when a building permit is exempt. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in Belvedere, CA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Belvedere, CA via: (415) 435-8915, city inspection page. Inspections are conducted Monday through Thursday, generally 8:00 a.m. to 3:00 p.m. Requests received by 11:59 p.m. the day before are scheduled for the next inspection day. If a callback number is left, the inspector may provide a two-hour inspection window on the inspection day..
last verified April 2026 source City of Belvedere Planning & Building Department ↗ entry id permits/california/marin/belvedere

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Belvedere Planning & Building Department before applying. Jaspector is not legal advice.