jaspector
County building permits

Unincorporated Madera County

How to apply for a building permit in unincorporated Madera County, California. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 6
§ 01

Permit authority

Madera County Community and Economic Development Department, Building Division

Street address
200 W. 4th Street, Suite 3100, Madera, CA 93637
Coverage
Madera County states its Building Division regulates buildings and structures within the unincorporated area of the county; unincorporated Madera County relies on this county department for building permits.
Online portal
POSSE permit portal
POSSE
§ 02

When a permit is required

Permit triggers and exempt work for Madera County

Madera County states it is unlawful to erect, construct, enlarge, alter, repair, relocate, or convert buildings and structures in the unincorporated county without first securing a permit, and the county specifically calls out buildings, pools, electrical work, plumbing, heating and cooling facilities, mobile home installations, and demolition of structures over 120 square feet. The county's exemption handout also says that for projects other than the listed exemptions, a permit is likely required.

One-story detached accessory buildings such as tool sheds, storage sheds, and playhouses not exceeding 120 square feet
Fences not over 6 feet high
Oil derricks
Retaining walls not over 4 feet high, measured from bottom of footing to top of wall, unless supporting a surcharge or impounding certain liquids
Water tanks supported directly on grade if capacity does not exceed 5,000 gallons and the height-to-diameter or width ratio does not exceed 2:1
Sidewalks and driveways not more than 30 inches above adjacent grade, not over a basement or story below, not part of an accessible route, and not within the public right-of-way
Painting, papering, tiling, carpeting, cabinets, countertops without sinks, and similar finish work
Temporary motion picture, television, and theater stage sets and scenery
Prefabricated above-ground pools accessory to single-family residences that are less than 24 inches deep and do not exceed 5,000 gallons
Shade cloth structures for nursery or agricultural purposes, excluding service systems
Swings and other playground equipment accessory to detached one- and two-family dwellings
Window awnings on Group R-3 and Group U occupancies that project no more than 54 inches and do not require additional support
Nonfixed and movable fixtures, cases, racks, counters, and partitions not over 5 feet 9 inches high
  • Exempt One-story detached accessory buildings such as tool sheds, storage sheds, and playhouses not exceeding 120 square feet
  • Exempt Fences not over 6 feet high
  • Exempt Oil derricks
  • Exempt Retaining walls not over 4 feet high, measured from bottom of footing to top of wall, unless supporting a surcharge or impounding certain liquids
  • Exempt Water tanks supported directly on grade if capacity does not exceed 5,000 gallons and the height-to-diameter or width ratio does not exceed 2:1
  • Exempt Sidewalks and driveways not more than 30 inches above adjacent grade, not over a basement or story below, not part of an accessible route, and not within the public right-of-way
  • Exempt Painting, papering, tiling, carpeting, cabinets, countertops without sinks, and similar finish work
  • Exempt Temporary motion picture, television, and theater stage sets and scenery
  • Exempt Prefabricated above-ground pools accessory to single-family residences that are less than 24 inches deep and do not exceed 5,000 gallons
  • Exempt Shade cloth structures for nursery or agricultural purposes, excluding service systems
  • Exempt Swings and other playground equipment accessory to detached one- and two-family dwellings
  • Exempt Window awnings on Group R-3 and Group U occupancies that project no more than 54 inches and do not require additional support
  • Exempt Nonfixed and movable fixtures, cases, racks, counters, and partitions not over 5 feet 9 inches high

Note: The county exemption sheet says separate planning approval may still be required for location, especially for sheds, fences, retaining walls, and tanks. It also states that if otherwise exempt work includes plumbing, electrical, or mechanical work, separate trade permits will still be required.

Required documents
  • Completed permit application
  • 11 x 17 plot plan, floor plan, and elevation drawings
  • Project valuation
  • Owner or contractor contact information
  • Contractor or owner authorization form
  • Plan sets or construction documents needed for review
  • Operational statement where required
  • Civil or grading drawings where required
  • Environmental health clearance where required
  • Fire review items where required
  • Residential plan submittal information such as occupancy data, design criteria, utility material specifications, and design professional information where required
Building code
Madera County states it has adopted the California Building Code as mandated by the State of California. Current public county plan-submittal documents also reference California residential, electrical, plumbing, mechanical, green building, and energy code requirements, but the main public pages reviewed do not clearly identify the exact currently enforced Title 24 edition year.
Permit validity
County-published materials are not fully consistent. A current swimming pool permit application says a permit expires if work does not commence within one year of issuance, and also expires if work stops for more than 180 days from the last valid inspection unless a one-time extension is timely requested. A separate county owner-builder and grading form says the permit becomes null and void if work is not commenced or if no inspections are called for within 180 days of issuance. Applicants should confirm the currently enforced expiration rule with the Building Division before relying on either form.
Owner-builder
Madera County publishes an owner-builder permit package explaining that owner-builders are exempt from licensure in limited circumstances, but must complete and return the owner-builder notice and acknowledgment before permit issuance. The county warns that the property owner, not an agent, must execute the required owner-builder acknowledgment and that owner-builders assume legal and financial responsibility for the project and for verifying contractor licensing and workers' compensation coverage where applicable.
Contractor requirements
Madera County's permit requirements state contractors must have a current Madera County business license and a current California Contractors State License Board license. The owner-builder packet also states contractors are required by law to be licensed and bonded in California and to list their license numbers on permits and contracts.

Source: Madera County Community and Economic Development Department, Building Division ↗

§ 03

Application process

Typical processing: The county does not post a single general turnaround for all building permits on the main Building Division pages reviewed. Project-specific county forms give a 1 to 3 business day goal for qualifying expedited EV charging permits and about 2 to 6 weeks for swimming pool permit review.

  1. 01
    Confirm the project scope and parcel constraints first. County permit requirements say Planning, Environmental Health, Fire Marshal, Engineering, and Road or Public Works review may all be needed depending on zoning, setbacks, septic or well issues, fire access, flood zone conditions, grading, and driveway access.
  2. 02
    Prepare the permit package. County materials require a completed permit application, plot plan, floor plan, elevations, project valuation, owner or contractor information, and any required authorization forms. Depending on scope, the county also requires an operational statement, plan sets, civil or grading drawings, and other supporting construction documents.
  3. 03
    Submit through the county's online permit system when the permit type is available there, or submit directly to the Building Division for project types that are handled outside the standard online flow. The county's public pages state in-person submittals are accepted Monday through Friday and some project-specific applications instruct applicants to submit directly to mcbuilding@madera-county.com.
  4. 04
    Pay required application or plan review fees. County materials indicate applicants are invoiced or charged at submittal depending on permit type, and permit issuance does not occur until required fees and outside-agency sign-offs are complete.
  5. 05
    Respond to correction comments if the plan review identifies deficiencies. The county states applicants are notified after all reviewing departments complete compliance review.
  6. 06
    Receive permit issuance, keep the approved plans and job card at the site, and schedule required inspections as construction progresses.
  7. 07
    Pass final inspection before occupancy or project closeout.

Typical processing time: The county does not post a single general turnaround for all building permits on the main Building Division pages reviewed. Project-specific county forms give a 1 to 3 business day goal for qualifying expedited EV charging permits and about 2 to 6 weeks for swimming pool permit review.

Source: Madera County Community and Economic Development Department, Building Division ↗

§ 04

Fee schedule

Madera County building permit fees

Fee type
Amount
01
Plan check fee
Required where plan review applies, but the county does not publish a current general public dollar schedule on the pages reviewed. County application materials indicate applicants are invoiced or charged at submittal depending on permit type.
02
Permit fee formula
Mixed. County permit applications require project valuation for standard permits, while the county's online permit page states reroof and swimming pool permits use flat fees and some OTC permits use streamlined or flat-fee processing.
03
Reinspection fee
A reinspection fee of a minimum one hour at the current rate may be assessed when work is incomplete or corrections are not made. The demolition section on the Building Division page also notes reinspection fees may be charged for jobs not ready for inspection, missing permit cards or plans, failure to provide access, or deviations from approved plans.

The county's online permits page says the portal accepts MasterCard, Visa, and American Express. County materials also indicate payment timing varies by permit type: some applications say fees are collected at submittal, some say fees are invoiced, and permit issuance waits for required fees to be paid.

§ 05

Required inspections

Scheduling and sequence

How to schedule
Scheduling deadline
Inspection requests should be made at least 24 hours in advance. County EV charging guidance says inspection requests received before 5:00 PM can usually be scheduled for the following inspection day.
Inspection hours
Field inspectors' office hours are Monday through Friday, 8:00 AM to 4:00 PM.

Typical sequence: The county's inspection handout gives a rough order that includes ground plumbing and setbacks, foundation, concrete block where applicable, floor framing, sub-floor sheathing, roof and shear wall nailing, framing with rough plumbing, mechanical, and electrical, sewer or septic connections, Title 24 insulation, lath or drywall nailing, shower pan, gas test, gas piping, electrical meter set, and final inspection. Certificate of occupancy is issued after satisfactory final inspection.

Source: Madera County Community and Economic Development Department, Building Division ↗

§ 06

Frequently asked

Common questions about unincorporated Madera County permits

01 Do I need a building permit in unincorporated Madera County, CA?
Madera County states it is unlawful to erect, construct, enlarge, alter, repair, relocate, or convert buildings and structures in the unincorporated county without first securing a permit, and the county specifically calls out buildings, pools, electrical work, plumbing, heating and cooling facilities, mobile home installations, and demolition of structures over 120 square feet. The county's exemption handout also says that for projects other than the listed exemptions, a permit is likely required.
02 How much does a building permit cost in unincorporated Madera County, CA?
Building permit fees in unincorporated Madera County, CA are set by the local building department and vary by project type and valuation. Fees are calculated as: Mixed. County permit applications require project valuation for standard permits, while the county's online permit page states reroof and swimming pool permits use flat fees and some OTC permits use streamlined or flat-fee processing.. Plan check fee: Required where plan review applies, but the county does not publish a current general public dollar schedule on the pages reviewed. County application materials indicate applicants are invoiced or charged at submittal depending on permit type..
03 How do I apply for a building permit in unincorporated Madera County, CA?
To apply for a building permit in unincorporated Madera County, CA, follow these steps: 1. Confirm the project scope and parcel constraints first. County permit requirements say Planning, Environmental Health, Fire Marshal, Engineering, and Road or Public Works review may all be needed depending on zoning, setbacks, septic or well issues, fire access, flood zone conditions, grading, and driveway access. 2. Prepare the permit package. County materials require a completed permit application, plot plan, floor plan, elevations, project valuation, owner or contractor information, and any required authorization forms. Depending on scope, the county also requires an operational statement, plan sets, civil or grading drawings, and other supporting construction documents. 3. Submit through the county's online permit system when the permit type is available there, or submit directly to the Building Division for project types that are handled outside the standard online flow. The county's public pages state in-person submittals are accepted Monday through Friday and some project-specific applications instruct applicants to submit directly to mcbuilding@madera-county.com. 4. Pay required application or plan review fees. County materials indicate applicants are invoiced or charged at submittal depending on permit type, and permit issuance does not occur until required fees and outside-agency sign-offs are complete. 5. Respond to correction comments if the plan review identifies deficiencies. The county states applicants are notified after all reviewing departments complete compliance review. 6. Receive permit issuance, keep the approved plans and job card at the site, and schedule required inspections as construction progresses. 7. Pass final inspection before occupancy or project closeout.
04 How long does it take to get a building permit in unincorporated Madera County, CA?
Building permit processing times in unincorporated Madera County, CA typically run The county does not post a single general turnaround for all building permits on the main Building Division pages reviewed. Project-specific county forms give a 1 to 3 business day goal for qualifying expedited EV charging permits and about 2 to 6 weeks for swimming pool permit review.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in unincorporated Madera County, CA?
Not all construction work requires a permit in unincorporated Madera County, CA. The following work is generally exempt: One-story detached accessory buildings such as tool sheds, storage sheds, and playhouses not exceeding 120 square feet; Fences not over 6 feet high; Oil derricks; Retaining walls not over 4 feet high, measured from bottom of footing to top of wall, unless supporting a surcharge or impounding certain liquids; Water tanks supported directly on grade if capacity does not exceed 5,000 gallons and the height-to-diameter or width ratio does not exceed 2:1; Sidewalks and driveways not more than 30 inches above adjacent grade, not over a basement or story below, not part of an accessible route, and not within the public right-of-way; Painting, papering, tiling, carpeting, cabinets, countertops without sinks, and similar finish work; Temporary motion picture, television, and theater stage sets and scenery; Prefabricated above-ground pools accessory to single-family residences that are less than 24 inches deep and do not exceed 5,000 gallons; Shade cloth structures for nursery or agricultural purposes, excluding service systems; Swings and other playground equipment accessory to detached one- and two-family dwellings; Window awnings on Group R-3 and Group U occupancies that project no more than 54 inches and do not require additional support; Nonfixed and movable fixtures, cases, racks, counters, and partitions not over 5 feet 9 inches high. Note: The county exemption sheet says separate planning approval may still be required for location, especially for sheds, fences, retaining walls, and tanks. It also states that if otherwise exempt work includes plumbing, electrical, or mechanical work, separate trade permits will still be required. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in unincorporated Madera County, CA?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in unincorporated Madera County, CA via: (559) 675-5206, (559) 675-7821, POSSE permit portal. Inspection requests should be made at least 24 hours in advance. County EV charging guidance says inspection requests received before 5:00 PM can usually be scheduled for the following inspection day..
last verified April 2026 source Madera County Community and Economic Development Department, Building Division ↗ entry id permits/california/madera/unincorporated

Educational reference. Permit rules and fees change — confirm current requirements directly with Madera County Community and Economic Development Department, Building Division before applying. Jaspector is not legal advice.