jaspector
§ AR Boone County
City building permits

City of Bellefonte

How to apply for a building permit in City of Bellefonte, Arkansas. Permit authority, application steps, fees, and inspection requirements.

Last verified
April 2026
On this page 5
§ 01

Permit authority

City of Bellefonte

Street address
705 Bellefonte Princess Road, Bellefonte, AR 72623
Coverage
City of Bellefonte.
§ 02

When a permit is required

Permit triggers and exempt work for Bellefonte

Not fully published in a separate ordinance page; the public application implies new dwellings and other regulated work.

Roofing projects do not require a plat of survey
Siding projects do not require a plat of survey
  • Exempt Roofing projects do not require a plat of survey
  • Exempt Siding projects do not require a plat of survey

Note: No broader exempt-work list was found.

Required documents
  • Plat of survey for new structures and alterations other than roofing or siding
  • Application details
  • Contractor information
  • Construction value
  • Zoning information
Building code
The form includes a building code review section, but the adopted code text was not public in the retrieved source.
Owner-builder
Application must be authorized by the owner of record or agent.
Contractor requirements
Contractor or builder contact information is requested; no explicit licensing rule located in the public form.
§ 03

Application process

Application → plan check → issuance → inspection → final

  1. 01
    The residential permit application includes owner, applicant, contractor, project, zoning, and review fields.
  2. 02
    A plat of survey must accompany applications for new structures or alterations, including decks, pools, and sheds, but not roofing or siding.
  3. 03
    The applicant agrees not to occupy the building until inspections are complete and a certificate of occupancy is issued.

Source: City of Bellefonte ↗

§ 04

Required inspections

Scheduling and sequence

How to schedule
  • Applicant may schedule necessary inspections as agent (other)

Typical sequence: Occupancy is prohibited until all inspections are complete and a certificate of occupancy is issued.

§ 05

Frequently asked

Common questions about Bellefonte permits

01 Do I need a building permit in Bellefonte, AR?
Not fully published in a separate ordinance page; the public application implies new dwellings and other regulated work.
02 How do I apply for a building permit in Bellefonte, AR?
To apply for a building permit in Bellefonte, AR, follow these steps: 1. The residential permit application includes owner, applicant, contractor, project, zoning, and review fields. 2. A plat of survey must accompany applications for new structures or alterations, including decks, pools, and sheds, but not roofing or siding. 3. The applicant agrees not to occupy the building until inspections are complete and a certificate of occupancy is issued.
03 What work is exempt from building permits in Bellefonte, AR?
Not all construction work requires a permit in Bellefonte, AR. The following work is generally exempt: Roofing projects do not require a plat of survey; Siding projects do not require a plat of survey. Note: No broader exempt-work list was found. When in doubt, confirm with the local building department before starting work.
04 How do I schedule a building inspection in Bellefonte, AR?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in Bellefonte, AR via: Applicant may schedule necessary inspections as agent.
last verified April 2026 source City of Bellefonte ↗ entry id permits/arkansas/boone/bellefonte

Educational reference. Permit rules and fees change — confirm current requirements directly with City of Bellefonte before applying. Jaspector is not legal advice.

§   Adjacent

Other jurisdictions in Boone County.

Same county, different permit office. Click for that jurisdiction's full guide.