§ 01

Permit authority

Jefferson County Department of Development Services

Street address
Jefferson County Courthouse complex, 716 Richard Arrington Jr. Blvd. N, Birmingham, AL 35203
Coverage
Development Services accepts building permits for unincorporated Jefferson County and only for municipalities the county expressly serves by agreement. The county's procedures say properties outside unincorporated Jefferson County or the cities it serves are not accepted.
Online portal
Accela Citizen Access / ePermitJC
Accela Citizen Access / ePermitJC
Additional resources
§ 02

When a permit is required

Permit triggers and exempt work for Jefferson County

County process covers building, addition, alteration, miscellaneous building, demolition, and stand alone trade permits for electrical, gas, and plumbing/mechanical work in the county service area.

For minor repair questions, applicants should verify directly with Development Services before assuming work is exempt.
  • Exempt For minor repair questions, applicants should verify directly with Development Services before assuming work is exempt.
Required documents
  • Permit application
  • plans
  • contractor licensing registration where required
  • septic or sewer approval where applicable
  • and any plan review materials required by the permit type.
Permit validity
Refer to the county's Expiration of Permits document in ePermitJC; the public portal indicates time limitations apply by record type.
Contractor requirements
County requires contractor licensing setup before application for permits that require a licensed professional, including a copy of the state license and a current Jefferson County business license.
§ 03

Application process

Typical processing: Architectural plans are typically reviewed within 10 business days depending on complexity.

  1. 01
    Register contractor licensing with Development Services if the permit type requires a licensed professional; the county requires a state license and current Jefferson County business license before the contractor can apply.
  2. 02
    Obtain prerequisite septic approval from the Jefferson County Health Department or sewer approval from Environmental Services before submitting a building permit when applicable.
  3. 03
    Create or log into ePermitJC and submit the permit application, plans, and supporting data, or submit a hard copy package in person.
  4. 04
    Pay application and review fees after the application is deemed sufficient and the county invoices the applicant.
  5. 05
    County staff route plans for review; the county states architectural plans are typically reviewed within 10 business days depending on complexity.
  6. 06
    Schedule inspections online or by phone after permit issuance; when all required inspections pass, download the Certificate of Completion or Certificate of Occupancy from ePermitJC.

Typical processing time: Architectural plans are typically reviewed within 10 business days depending on complexity.

Source: Jefferson County Department of Development Services ↗

§ 04

Fee schedule

Jefferson County building permit fees

Fee type
Amount
01
Minimum permit fee
$50 for miscellaneous building permits up to $5,000 valuation; trade permits up to $5,000 are $50 plus administrative and technology fees; demolition minimum is $100.
02
Plan check fee
Commercial building architectural plan review is $200 per commercial plan set; miscellaneous and trade architectural plan review is $100 if needed.
03
Permit fee formula
Valuation based for most building and trade permits plus a $50 administrative fee and $10 technology fee on permits/applications available through Accela.
04
Reinspection fee
Failed, incomplete, or late-cancel inspections are $55 each; permit extension is $50; stop work is double permit cost; work commencing before permit issuance is double permit cost for the first offense and triple for additional offenses.

Online payment by eCheck or accepted credit/debit cards; hard copy applications can be paid by exact cash, check, or accepted cards.

Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.

§ 05

Required inspections

Scheduling and sequence

How to schedule
  • 205-325-5321 (phone)

Typical sequence: Permit issuance, rough inspections as applicable, final inspection, then Certificate of Completion or Certificate of Occupancy

Failed inspections and inspections canceled after the cutoff incur a fee; revisions are required if the work differs from the approved plans.

§ 06

Frequently asked

Common questions about unincorporated Jefferson County permits

01 Do I need a building permit in unincorporated Jefferson County, AL?
County process covers building, addition, alteration, miscellaneous building, demolition, and stand alone trade permits for electrical, gas, and plumbing/mechanical work in the county service area.
02 How much does a building permit cost in unincorporated Jefferson County, AL?
Building permit fees in unincorporated Jefferson County, AL are set by the local building department and vary by project type and valuation. The minimum permit fee is $50 for miscellaneous building permits up to $5,000 valuation; trade permits up to $5,000 are $50 plus administrative and technology fees; demolition minimum is $100.. Fees are calculated as: Valuation based for most building and trade permits plus a $50 administrative fee and $10 technology fee on permits/applications available through Accela.. Plan check fee: Commercial building architectural plan review is $200 per commercial plan set; miscellaneous and trade architectural plan review is $100 if needed..
03 How do I apply for a building permit in unincorporated Jefferson County, AL?
To apply for a building permit in unincorporated Jefferson County, AL, follow these steps: 1. Register contractor licensing with Development Services if the permit type requires a licensed professional; the county requires a state license and current Jefferson County business license before the contractor can apply. 2. Obtain prerequisite septic approval from the Jefferson County Health Department or sewer approval from Environmental Services before submitting a building permit when applicable. 3. Create or log into ePermitJC and submit the permit application, plans, and supporting data, or submit a hard copy package in person. 4. Pay application and review fees after the application is deemed sufficient and the county invoices the applicant. 5. County staff route plans for review; the county states architectural plans are typically reviewed within 10 business days depending on complexity. 6. Schedule inspections online or by phone after permit issuance; when all required inspections pass, download the Certificate of Completion or Certificate of Occupancy from ePermitJC.
04 How long does it take to get a building permit in unincorporated Jefferson County, AL?
Building permit processing times in unincorporated Jefferson County, AL typically run Architectural plans are typically reviewed within 10 business days depending on complexity.. Timelines can vary based on project complexity and current department workload.
05 What work is exempt from building permits in unincorporated Jefferson County, AL?
Not all construction work requires a permit in unincorporated Jefferson County, AL. The following work is generally exempt: For minor repair questions, applicants should verify directly with Development Services before assuming work is exempt.. When in doubt, confirm with the local building department before starting work.
06 How do I schedule a building inspection in unincorporated Jefferson County, AL?
Once your permit is issued and work reaches an inspection milestone, you can schedule a building inspection in unincorporated Jefferson County, AL via: 205-325-5321.