When a permit is required
Permit triggers and exempt work for Valley Grande
Ordinance covers all buildings, structures, or alterations requiring a building permit under the city building code.
- Building permit application
- 911 address
- Project description
- Square footage/value calculation
- Owner information
- Builder information
- Electrician license number
- HVAC license number
- Plumber license number
- State license numbers
- Valley Grande business license numbers for electricians, HVAC contractors, and plumbers
- Stamped plans for commercial construction when requested by staff
- Building code
- City of Valley Grande Alabama Building Code; fee ordinance references Section 109 of the IBC-2003.
- Owner-builder
- Application includes homeowner information and appears to allow homeowner applicants, but no separate owner-builder policy statement was located.
- Contractor requirements
- The application requires state license numbers and Valley Grande business license numbers for electrician, HVAC, and plumber.
Application process
Application → plan check → issuance → inspection → final
- 01 Complete the Building Permit Application PDF.
- 02 Provide the required project data, 911 address, ownership and contractor information, and any required plans or stamped copies.
- 03 Submit the application to the Valley Grande Public Safety Department at 5914 AL Hwy 22.
- 04 City staff review the package.
- 05 Pay the calculated fee and required inspection charges.
- 06 The building inspector completes required inspections.
- 07 Temporary power is released after permit process and satisfactory inspections; permanent power is released after the certificate of occupancy permit is issued.
Source: Valley Grande Public Safety Department / Building Inspector ↗
Fee schedule
Valley Grande building permit fees
Ordinance also references inspection charges of $75 and a minimum of four inspections in several valuation tiers.
Fees change periodically. Confirm at the official fee schedule ↗ before budgeting.
Required inspections
Scheduling and sequence
- Valley Grande Public Safety Department / Building Inspector (in_person)
- (334) 872-0104 (phone)
Typical sequence: Permit application review, payment, required inspections, temporary power release after satisfactory inspection, and permanent power after certificate of occupancy permit issuance.
Source: Valley Grande Public Safety Department / Building Inspector ↗
Frequently asked
Common questions about Valley Grande permits
01 Do I need a building permit in Valley Grande, AL? ▸
02 How much does a building permit cost in Valley Grande, AL? ▸
03 How do I apply for a building permit in Valley Grande, AL? ▸
04 How do I schedule a building inspection in Valley Grande, AL? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Valley Grande Public Safety Department / Building Inspector before applying. Jaspector is not legal advice.