City Building Permits

Auburn (Pierce County Portion), WA Building Permit Guide

How to apply for a building permit in Auburn (Pierce County Portion), Washington. Permit authority, application steps, fees, and inspection requirements.

Washington Pierce County Updated March 2026

Permit Authority

City of Auburn (primarily King County but includes portions in Pierce County).

Department
Community Development Department
Phone
(253) 931-3020

Online Permit Portal

Platform:Account required: Yes • Submission: In-person only

Application Process

  1. Confirm permit requirements - Unattached accessory structures under 200 sq ft may not need permit.
  2. Prepare detailed plans including specifications and drawings.
  3. Submit application to Auburn Building Department (online or in-person).
  4. Pay application fee.
  5. Plan review process (several weeks).
  6. Receive permit upon approval and commence work.
  7. Schedule required inspections.

Typical processing time: Plan review typically takes several weeks.

Source: Community Development Department

General Requirements

A building permit is required for construction within the City of Auburn.

Required Documents

  • Completed permit application
  • Detailed plans and specifications
  • Construction drawings
Permit validity
Building permits valid for 180 days from issuance. Extension fee: $50 (apply before expiration).
Building code
2021 Washington State Building Code with amendments.
Owner-builder
Homeowners may act as owner-builders; confirm requirements with Building Department.
Contractor requirements
All contractors must be registered with Washington State L&I. Building permits valid for 180 days from issuance. Late fee for work without permit: Equal to cost of original permit. Fees can be paid when Certificate of Occupancy issued rather than at permit issuance.

Fees

Plan check fee
Varies by project complexity.
Permit fee formula
Flat rate: $15.00 per $1,000 of estimated cost for new construction, additions/alterations, porches/decks/garages. Swimming pools $200 minimum. Demolition $200 minimum.
Trade permit fee
Varies by permit type and scope.
Reinspection fee
Varies by permit type and scope.
Payment note
Contact Building Department for payment methods.

Work That Does NOT Require a Permit

Contact the Community Development Department to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • Building Department (phone)
Scheduling deadline
Contact Building Department for scheduling details.
Inspection hours
Monday-Friday during business hours (confirm with Building Department)
Time windows
Inspections required at various project phases.

Typical inspection sequence: Inspections required at various project phases. Final inspection required.

Contact Building Department for remote inspection options.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Community Development Department before applying.

Need help with your project?

Navigating permits in Auburn (Pierce County Portion) can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Pierce County

View all Pierce County jurisdictions →