Center Township, PENNSYLVANIA Building Permit Guide
How to apply for a building permit in Center Township, Pennsylvania. Permit authority, application steps, fees, and inspection requirements.
Permit Authority
All properties within Center Township, Butler County. The township's permit page directs applicants to contact Kraft Municipal Group for building permits.
- Department
- Center Township Building Permits / Zoning, with permit processing assistance from Kraft Municipal Group
- Address
- 150 Henricks Road, Butler, PA 16001-8472
- Phone
- (724) 282-7805 option 2
Online Permit Portal
Platform: • Account required: No • Submission: In-person only
Additional resources:
Application Process
- Contact Center Township or Kraft Municipal Group and confirm the permit type and required packet.
- Submit the completed application, application fee, and supporting documents including drawings and workers compensation documentation.
- For residential projects, Kraft states the building inspector has a three-week review period; for non-residential projects, six weeks is allotted.
- After approval, the applicant is contacted to pick up the permit and pay the balance due.
- At pickup, the applicant signs permit copies and receives the inspection checklist for the project.
- Do not begin construction until the approved permit is issued and paid.
- Complete required inspections and final closeout within the permit term.
Typical processing time: Residential review period up to 3 weeks; non-residential review period up to 6 weeks
General Requirements
Kraft's permit application triggers review for construction, enlargement, alteration, structural repair, relocation, demolition, change of use, and installation or alteration of electrical, mechanical, plumbing, and energy-related work. Center Township's pool application also requires permits for swimming pools and spas.
Required Documents
- Completed permit application
- Application fee
- Completed zoning application where applicable
- Two sets of drawings
- Plot plan
- Construction drawings
- Any required trade permits
- Sewage approval if needed
- Workers compensation insurance or notarized exemption form
- Permit validity
- Permits are valid for one year from date of issuance. Written extensions of up to 180 days each may be granted for justifiable cause, with an additional fee.
- Building code
- Pennsylvania Uniform Construction Code (UCC). Township forms reference IRC-based residential provisions and township permit coordination through code officials and Kraft.
- Owner-builder
- Kraft states the permit applicant may be the owner or the owner's agent
- Contractor requirements
- Proof of contractor workers compensation insurance or notarized exemption form is required. For residential home improvement work over $5,000, Pennsylvania Home Improvement Contractor registration requirements may apply at the state level.
Fees
- Minimum permit fee
- $100
- Plan check fee
- Included in the permit review process; a separate plan-check fee table was not clearly posted
- Permit fee formula
- Kraft's current permit application states the application fee is $100 for residential property and $250 for non-residential property. The zoning permit review application fee is $50 for residential property.
- Reinspection fee
- Kraft states performing work without a permit results in doubling of all permit fees. Extension requests also require an additional fee.
- Penalty (no permit)
- Double all permit fees for building without a permit
- Payment note
- Application fees are submitted up front and applied to the total permit cost, with the balance due at permit pickup
Fees change. Verify current amounts at the official fee schedule.
Work That Does NOT Require a Permit
Contact the Center Township Building Permits / Zoning, with permit processing assistance from Kraft Municipal Group to confirm whether your project requires a permit before starting work.
Inspections
How to Schedule
- (724) 287-1945 or centertownshipcodes@aol.com (phone)
Typical inspection sequence: Permit issuance, required trade and building inspections per the project checklist, then final inspection
Additional Resources
- Building code: Pennsylvania Uniform Construction Code (UCC). Township forms reference IRC-based residential provisions and township permit coordination through code officials and Kraft.
- Zoning information: View zoning info
- Building Permits
- Kraft Municipal Group Permitting
- Building Permit Packet
- Pool Application
- License lookup guide: Pennsylvania Contractor License Requirements
- Contract template: Pennsylvania Homeowner-Contractor Agreement
- Pennsylvania hub: Pennsylvania Contractor License & Permit Hub
Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Center Township Building Permits / Zoning, with permit processing assistance from Kraft Municipal Group before applying.
Need help with your project?
Navigating permits in Center Township can be complicated.
Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.
Learn how Jaspector worksOther cities in Butler County
View all Butler County jurisdictions →