Permit Authority

All properties within the incorporated City of Port Jervis.

Department
City of Port Jervis Building / Code Enforcement Office
Address
20 Hammond Street, Port Jervis, NY 12771
Phone
845-858-4080

Online Permit Portal

Platform: In-person / Phone • Account required: No • Submission: In-person only

Application Process

  1. Contact the Building / Code Enforcement Office at 845-858-4080.
  2. Submit a building permit application without first obtaining a permit is prohibited by city code.
  3. Submit completed permit application and required construction documents.
  4. City staff reviews for compliance with the Uniform Code and city code.
  5. Fire Inspector conducts fire-system and life-safety review.
  6. Pay applicable permit and plan-check fees.
  7. Obtain permit before beginning construction work.
  8. Schedule required inspections.
  9. Obtain certificate of occupancy or certificate of compliance before use.

Typical processing time: Typical time varies; confirm with the city office.

Source: City of Port Jervis Building / Code Enforcement Office

General Requirements

City code states no person may commence work requiring a building permit without first obtaining one from the city.

Required Documents

  • Completed permit application
  • Site plan
  • Construction plans
  • Building Code compliance documentation
Permit validity
Varies per city code; confirm with the city office.
Building code
New York State Uniform Fire Prevention and Building Code (2025 code update, effective December 31, 2025)
Owner-builder
Owner-builders must comply with city code requirements.
Contractor requirements
Contractors must comply with local licensing and bonding requirements.

Fees

Minimum permit fee
Confirm with city office
Plan check fee
Confirm with city office
Permit fee formula
Confirm with city office
Trade permit fee
Confirm with city office
Reinspection fee
Confirm with city office
Penalty (no permit)
Confirm with city office
Payment note
Confirm current charges with the Building / Code Enforcement Office

Work That Does NOT Require a Permit

Contact the City of Port Jervis Building / Code Enforcement Office to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • 845-858-4080 (Building); 845-858-4020 (Fire Inspector) (phone)
  • 20 Hammond Street, Port Jervis, NY 12771 (in-person)
Scheduling deadline
Confirm with the city office
Inspection hours
Confirm with the city office
Time windows
Confirm with the city office

Typical inspection sequence: City code requires a certificate of occupancy or certificate of compliance before use, with Code Enforcement Officer inspecting before issuance.

Confirm if remote inspections are available with the city office.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the City of Port Jervis Building / Code Enforcement Office before applying.

Frequently Asked Questions

Port Jervis Building Permit FAQ

Do I need a building permit in Port Jervis, NY?
City code states no person may commence work requiring a building permit without first obtaining one from the city.
How much does a building permit cost in Port Jervis, NY?
The minimum permit fee is Confirm with city office. Fees are calculated as: Confirm with city office. Plan check fee: Confirm with city office.
How do I apply for a building permit in Port Jervis, NY?
1. Contact the Building / Code Enforcement Office at 845-858-4080. 2. Submit a building permit application without first obtaining a permit is prohibited by city code. 3. Submit completed permit application and required construction documents. 4. City staff reviews for compliance with the Uniform Code and city code. 5. Fire Inspector conducts fire-system and life-safety review. 6. Pay applicable permit and plan-check fees. 7. Obtain permit before beginning construction work. 8. Schedule required inspections. 9. Obtain certificate of occupancy or certificate of compliance before use.
How long does it take to get a building permit in Port Jervis, NY?
Typical processing time is Typical time varies; confirm with the city office..
How do I schedule a building inspection in Port Jervis, NY?
Inspections can be scheduled via: 845-858-4080 (Building); 845-858-4020 (Fire Inspector), 20 Hammond Street, Port Jervis, NY 12771. Confirm with the city office.

Need help with your project?

Navigating permits in Port Jervis can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Orange County

View all Orange County jurisdictions →