City Building Permits
Village of Malone, NY - Building Permit Guide
How to apply for a building permit in Village of Malone, New York. Permit authority, application steps, fees, and inspection requirements.
Permit Authority
All properties within the incorporated Village of Malone (located within Town of Malone).
- Department
- Code Enforcement Office
- Address
- 343 West Main Street, Malone, NY 12953
- Phone
- 518-483-4570
Online Permit Portal
Platform: Village Code Enforcement Office • Account required: No • Submission: In-person only
Additional resources:
Application Process
- Contact the Village Code Enforcement Office to discuss your project.
- Obtain permit application forms from the village office.
- Prepare construction plans and site plan per code requirements.
- Submit completed application and documents to Code Enforcement Office.
- Office reviews application for completeness.
- Pay permit fee.
- Receive permit and schedule required inspections.
- Pass inspections before project completion.
Typical processing time: Typically 1-3 weeks for initial review after submission.
Source: Code Enforcement Office
General Requirements
Building permits are required for construction, enlargement, alteration, improvement, relocation, demolition, and solid-fuel appliance work that must conform to the New York State Uniform Code or Energy Code.
Required Documents
- Completed permit application
- Site plan
- Construction plans
- Applicant information
- Permit validity
- Varies; contact Code Enforcement Office for details.
- Building code
- New York State Uniform Fire Prevention and Building Code; New York State Energy Conservation Construction Code
- Owner-builder
- Verify owner-builder regulations with the Code Enforcement Office before proceeding.
- Contractor requirements
- Contractors must hold valid licenses and insurance as required by New York State.
Fees
- Minimum permit fee
- Contact Code Enforcement Office
- Plan check fee
- Contact office
- Permit fee formula
- Contact office for fee structure
- Trade permit fee
- Contact office
- Reinspection fee
- Contact office
- Penalty (no permit)
- Contact office
- Payment note
- Contact office for payment methods and options.
Work That Does NOT Require a Permit
Contact the Code Enforcement Office to confirm whether your project requires a permit before starting work.
Inspections
How to Schedule
- 518-483-4570 (phone)
- Scheduling deadline
- Contact Code Enforcement Office for scheduling deadlines.
- Inspection hours
- Contact office for office hours.
- Time windows
- Contact office for inspection windows.
Typical inspection sequence: Contact office for inspection sequence requirements.
Contact office regarding remote inspection options.
Additional Resources
- Building code: New York State Uniform Fire Prevention and Building Code; New York State Energy Conservation Construction Code
- Verify contractor license: CSLB License Lookup (California contractors only)
- License lookup guide: New York Contractor License Requirements
- Contract template: New York Homeowner-Contractor Agreement
- New York hub: New York Contractor License & Permit Hub
Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Code Enforcement Office before applying.
Frequently Asked Questions
Village of Malone Building Permit FAQ
- Do I need a building permit in Village of Malone, NY?
- Building permits are required for construction, enlargement, alteration, improvement, relocation, demolition, and solid-fuel appliance work that must conform to the New York State Uniform Code or Energy Code.
- How much does a building permit cost in Village of Malone, NY?
- The minimum permit fee is Contact Code Enforcement Office. Fees are calculated as: Contact office for fee structure. Plan check fee: Contact office.
- How do I apply for a building permit in Village of Malone, NY?
- 1. Contact the Village Code Enforcement Office to discuss your project. 2. Obtain permit application forms from the village office. 3. Prepare construction plans and site plan per code requirements. 4. Submit completed application and documents to Code Enforcement Office. 5. Office reviews application for completeness. 6. Pay permit fee. 7. Receive permit and schedule required inspections. 8. Pass inspections before project completion.
- How long does it take to get a building permit in Village of Malone, NY?
- Typical processing time is Typically 1-3 weeks for initial review after submission..
- How do I schedule a building inspection in Village of Malone, NY?
- Inspections can be scheduled via: 518-483-4570. Contact Code Enforcement Office for scheduling deadlines..
Need help with your project?
Navigating permits in Village of Malone can be complicated.
Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.
Learn how Jaspector worksOther cities in Franklin County