County Building Permits

Macoupin County Building Permit Guide (Unincorporated Area)

How to apply for a building permit in unincorporated Macoupin County, Illinois. Permit authority, application steps, fees, and inspection requirements.

Illinois Updated March 2026

Permit Authority

Covers all areas outside the incorporated limits of cities and villages. Macoupin County has no county-wide zoning ordinance.

Department
Macoupin County Supervisor of Assessments / GIS Department
Address
215 S. East St., Carlinville, IL 62626
Phone
(217) 854-3181 Ext. 5050

Online Permit Portal

Platform: Manual PDF • Account required: No • Submission: In-person only

Additional resources:

Application Process

  1. Determine if the project is in an unincorporated area and requires a septic system.
  2. Assign a 911 address through the 911 Coordinator (217-854-3181) if not already assigned.
  3. Obtain a Private Sewage Construction Permit from the Macoupin County Public Health Department (217-854-3223).
  4. Complete the Building Program Permit & PTAX-760 form.
  5. Submit form and $100 fee to the GIS Manager/Supervisor of Assessments.

Typical processing time: 5-10 business days

Source: Macoupin County Supervisor of Assessments / GIS Department

General Requirements

Any new construction that requires a septic system or any substantial improvement to existing structures in unincorporated areas.

Required Documents

  • Completed PTAX-760 form
  • Site plan
  • 911 address
  • Septic permit
Permit validity
Generally valid for 1 year or until construction completion.
Building code
Illinois Public Act 103-0510 (Statewide Mandatory Codes). Effective January 1, 2025: 2021 IBC (Commercial), 2021 IRC (Residential), 2021 IEBC (Existing Buildings), 2023 NEC (Electrical).
Owner-builder
Owner-builders are allowed and must comply with 2025 state mandates.
Contractor requirements
No county-wide general contractor license. Roofing contractors must be state-licensed. Plumbers must be state-licensed through IDFPR.

Fees

Minimum permit fee
$100.00
Plan check fee
None (County does not perform plan reviews for unincorporated residential)
Permit fee formula
Flat fee of $100.00 for the Building Program Permit
Payment note
Check or money order payable to Macoupin County Treasurer.

Fees change. Verify current amounts at the official fee schedule (effective 2026-03).

Work That Does NOT Require a Permit

  • Cosmetic work (painting, wallpapering, flooring)
  • Minor repairs not affecting structural integrity
  • Fences (in unincorporated areas only; verify setbacks)
  • Small sheds not requiring septic

Inspections

How to Schedule

Typical inspection sequence: The County does NOT perform building inspections for unincorporated residential projects. Commercial projects MUST contract with a qualified third-party inspector (ICC certified or IL licensed architect/engineer). Residential owners are responsible for ensuring code compliance via contract with the builder.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Macoupin County Supervisor of Assessments / GIS Department before applying.

Need help with your project?

Navigating permits in Unincorporated Macoupin County can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.
← Back to Macoupin County permit guides