Village of Brighton, ILLINOIS Building Permit Guide

How to apply for a building permit in Village of Brighton, Illinois. Permit authority, application steps, fees, and inspection requirements.

Illinois Macoupin County Updated March 2026

Permit Authority

Village limits (spans Macoupin and Jersey Counties).

Department
Village of Brighton Building & Zoning Department
Address
206 S. Main St., Brighton, IL 62012
Phone
(618) 372-8860

Online Permit Portal

Platform: PDF Form • Account required: No • Submission: In-person only

Application Process

  1. Complete Building Permit Application.
  2. Submit with site plan and 2 sets of plans.
  3. Zoning review and Building Inspector review.
  4. Pay fees and receive permit.

Typical processing time: 7-10 business days

Source: Village of Brighton Building & Zoning Department

General Requirements

All structures, fences, pools, decks, additions, and structural repairs.

Required Documents

  • Site plan (showing setbacks)
  • Blueprints
  • Contractor info
Permit validity
6 months to start; 1 year to finish.
Building code
2021 IRC/IBC.
Owner-builder
Allowed; must sign waiver if not using licensed contractors.
Contractor requirements
Must be registered with the Village.

Fees

Minimum permit fee
$20.00
Plan check fee
Included in permit fee
Permit fee formula
$0.05 to $0.10 per sq ft depending on use; flat $20 for fences/decks
Reinspection fee
$50.00 for failed inspections
Payment note
Cash or check.

Fees change. Verify current amounts at the official fee schedule (effective 2026-03).

Work That Does NOT Require a Permit

  • Painting, wallpapering
  • Tiling, carpeting, cabinets
  • Landscaping (non-structural)

Inspections

How to Schedule

  • (618) 372-8860 (at least 24h notice) (phone)
Scheduling deadline
At least 24 hours notice required
Inspection hours
Monday-Friday

Typical inspection sequence: Typical sequence: Footing, Framing, Final. Work must be ready before inspector arrives.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Village of Brighton Building & Zoning Department before applying.

Need help with your project?

Navigating permits in Village of Brighton can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Macoupin County

View all Macoupin County jurisdictions →