City Building Permits

Village of Downers Grove, ILLINOIS Building Permit Guide

How to apply for a building permit in Village of Downers Grove, Illinois. Permit authority, application steps, fees, and inspection requirements.

Illinois DuPage County Updated March 2026

Permit Authority

Serves the Village of Downers Grove.

Department
Community Development Department - Building Division
Address
850 Curtiss Street, First Floor, Downers Grove, IL 60515
Phone
(630) 434-5515

Online Permit Portal

Platform: Downers Grove Permit Portal • Account required: Yes • Submission: Online only

Application Process

  1. Create an account and submit permit application via the online portal.
  2. Upload digital documents and plans.
  3. Plan review occurs (initial review takes ~10 business days).
  4. Applicant receives notification of approval and fee total.
  5. Pay fees online.
  6. Permit issued via portal.

Typical processing time: 10 business days for initial review; 5 business days for revisions.

Source: Community Development Department - Building Division

General Requirements

Required for new construction, additions, structural repairs, basement finishing, decks, patios, driveways, fences, swimming pools, and water heater replacements.

Required Documents

  • Plat of Survey (2 copies for fences)
  • Construction plans
  • Contractor list
Permit validity
Varies by project type.
Building code
2021 IBC, 2021 IRC, 2020 NEC, Illinois Plumbing Code.
Owner-builder
Not specified; typically allowed with affidavit.
Contractor requirements
Contractors must be registered with the Village.

Fees

Minimum permit fee
$50 (Decks), $62 (Fences)
Plan check fee
~$120 for new homes; ~$60 for additions/alterations
Permit fee formula
Square footage-based ($0.35/sq. ft.) for new/additions; flat fees for specific items like fences.
Trade permit fee
Varies
Reinspection fee
Reinspection fees apply; cash bonds often required
Penalty (no permit)
Penalty for unpermitted work
Payment note
Online payment through the portal

Fees change. Verify current amounts at the official fee schedule (effective Current).

Work That Does NOT Require a Permit

  • Minor cosmetic work (painting, carpeting)
  • Replacing existing light fixtures (if no new wiring is added)

Important: Confirm exempt work categories with the Building Division before proceeding.

Inspections

How to Schedule

Scheduling deadline
Must be requested 48-72 hours in advance for reinspections.
Inspection hours
Monday - Friday, 7:30 AM - 4:30 PM
Time windows
Standard business hours.

Typical inspection sequence: Foundation, Rough-in, Final.

Contact the Building Division for remote inspection eligibility.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Community Development Department - Building Division before applying.

Need help with your project?

Navigating permits in Village of Downers Grove can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in DuPage County

View all DuPage County jurisdictions →