City Building Permits
Breese, ILLINOIS Building Permit Guide
How to apply for a building permit in Breese, Illinois. Permit authority, application steps, fees, and inspection requirements.
Permit Authority
Incorporated city limits of Breese.
- Department
- City of Breese Building and Zoning Department
- Address
- 500 North 1st Street, Breese, IL 62230
- Phone
- (618) 526-7731
- Website
- https://breese.org/
Online Permit Portal
Platform: City website • Account required: No • Submission: In-person only
Application Process
- Obtain application from City Hall or website.
- Submit two sets of construction plans and a site plan.
- Provide state license copies for plumbing and roofing contractors.
- Department reviews plans for compliance with local ordinances.
- Pay permit fees and receive issued permit.
Typical processing time: Approximately 2 weeks.
General Requirements
New construction, additions, structural alterations, fences, signs, and accessory structures over 120 sq. ft.
Required Documents
- Two sets of plans
- Site plan
- Contractor licenses
- Permit validity
- 1 year (Extensions available for $150).
- Building code
- IBC 2006, IRC 2006, NEC 2008, Illinois Plumbing Code.
- Owner-builder
- Owner-builders are allowed; must comply with all codes.
- Contractor requirements
- State licenses required for plumbers, roofers, and electricians.
Fees
- Minimum permit fee
- $50.00
- Plan check fee
- N/A
- Permit fee formula
- Square Footage x ICC Cost x 0.0015.
- Reinspection fee
- $30 for underground plumbing inspections; occupancy permit $69.
- Payment note
- Paid at City Hall.
Fees change. Verify current amounts at the official fee schedule.
Work That Does NOT Require a Permit
- Sheds under 120 sq. ft.
- Painting, carpeting, and similar finish work.
- Fences under 6 feet (though a permit is still required for placement verification).
Inspections
How to Schedule
- (618) 526-7151 (phone)
- Scheduling deadline
- 24-hour notice required.
- Inspection hours
- Monday-Friday, 7:30 AM - 4:00 PM
Typical inspection sequence: Typical sequence: Footings, framing, electrical, plumbing, final. Certificate of Occupancy issued upon final pass.
Additional Resources
- Building code: IBC 2006, IRC 2006, NEC 2008, Illinois Plumbing Code.
- Zoning information: View zoning info
- License lookup guide: Illinois Contractor License Requirements
- Contract template: Illinois Homeowner-Contractor Agreement
- Illinois hub: Illinois Contractor License & Permit Hub
Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the City of Breese Building and Zoning Department before applying.
Need help with your project?
Navigating permits in Breese can be complicated.
Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.
Learn how Jaspector worksOther cities in Clinton County