Permit Authority

Covers properties inside the City of Pine Lake. Permit coordination occurs through City Hall, and SafeBuilt handles plan review/inspection functions referenced by the city forms.

Department
City of Pine Lake Administration / Permitting and Licensing
Address
425 Allgood Road, Stone Mountain, GA 30083
Phone
404-999-4901

Online Permit Portal

Platform: City of Pine Lake permitting page and forms hub • Account required: No • Submission: In-person only

Additional resources:

Application Process

  1. Submit the Construction Pre-Planning Review form so the City Administrator can identify which approvals and permit path apply.
  2. Use the city permitting page to download and complete the applicable forms.
  3. Submit the building permit application and any required affidavits and supporting documents.
  4. Pay applicable fees.
  5. City and Building Code Compliance Consultant review the submission.
  6. Receive permit issuance.
  7. Complete inspections through the city/SafeBuilt process and obtain final inspection and CO/CC.

Typical processing time: Not posted as a single permit turnaround estimate on the city permitting page.

Source: City of Pine Lake Administration / Permitting and Licensing

General Requirements

Pine Lake states the process may include zoning compliance review, building permit, plan review, trade permits, inspections, and additional permits such as erosion control, demolition, and tree retention depending on scope.

Required Documents

  • Construction application/checklist
  • Building permit application
  • Homeowner affidavit if resident is doing work without a licensed contractor
  • Trade permit applications if needed
  • Tree removal permit if needed
  • Supporting plans and documents for review
Permit validity
The permit application states it becomes void if construction is not commenced within 180 days of issuance.
Building code
Georgia State Minimum Standard Codes administered locally by Pine Lake with local zoning review.
Owner-builder
Homeowner Affidavit for Building Permit is required where resident performs work without a licensed contractor. City form states the Building Department will only issue a permit to either a state licensed contractor or to the owner occupant.
Contractor requirements
State-licensed contractors are required unless the owner qualifies under the homeowner affidavit rules.

Fees

Minimum permit fee
Building Official and Administration Services billed at $123.42 per hour with a two-hour minimum for consulting services. A consolidated public fee schedule for all building permits was not cleanly published on the main permit page.
Plan check fee
Not clearly summarized on the landing page
Permit fee formula
Confirm directly with the city before submittal. Downloadable permit forms do not summarize a single universal schedule on the landing page.
Reinspection fee
HVAC permit form and inspection procedures imply separate inspection handling through SafeBuilt. Confirm charges directly with the city.
Payment note
City page states forms and payments can be completed online after process determination.

Fees change. Verify current amounts at the official fee schedule.

Work That Does NOT Require a Permit

Contact the City of Pine Lake Administration / Permitting and Licensing to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

Inspection hours
Monday through Thursday 8:30 a.m. to 12:30 p.m. and 1:30 p.m. to 4:30 p.m.
Time windows
All requests must be in by 12:00 p.m. for next-day inspection

Typical inspection sequence: Zoning compliance review; Building permit issuance; Trade permits; Progress inspections throughout construction; Final inspection and CO/CC.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the City of Pine Lake Administration / Permitting and Licensing before applying.

Need help with your project?

Navigating permits in Pine Lake can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in DeKalb County

View all DeKalb County jurisdictions →