Stuart, FL Building Permit Guide
How to apply for a building permit in Stuart, Florida. Permit authority, application steps, fees, and inspection requirements.
Permit Authority
Stuart runs its own city building division for projects inside city limits.
- Department
- City of Stuart Building Division
- Address
- 121 SW Flagler Avenue, Stuart, FL 34994
- Phone
- 772-288-5326
Online Permit Portal
Platform: OpenGov • Account required: Yes • Submission: Online only
Additional resources:
Application Process
- Confirm the property is inside Stuart city limits.
- Create or use an OpenGov account and select the Building and Permitting workflow.
- Submit the permit application and required plans/documents through OpenGov.
- If applicable, complete contractor registration and provide the required licensing and insurance documentation.
- Respond to plan review comments and pay fees before permit issuance.
- Obtain the permit before starting work, except in limited emergency-permit scenarios.
- Schedule inspections and obtain final approval.
Source: City of Stuart Building Division
General Requirements
Stuart's Building Division receives permit applications for structures ranging from office buildings to homes to fences and reviews plans for compliance with the Florida Building Code and city ordinances.
Required Documents
- Permit application
- Plans
- Contractor licensing and insurance documents
- Trade subcontractor information
- Building code
- 2023 Florida Building Code, 8th Edition, effective December 31, 2023
- Owner-builder
- Owner-builders may apply only for their own use and occupancy and may not hire unlicensed contractors.
- Contractor requirements
- Effective July 1, 2025, Stuart requires state registration or state certification where Florida law so provides. Certificates of Competency are no longer accepted.
Fees
- Minimum permit fee
- $106
- Permit fee formula
- $0-$50,000: greater of $106 or $22 for first $1,000 plus $6 per additional $1,000; $50,001-$100,000: $342 plus $7 per $1,000 above $50,000; $100,001-$500,000: $585 for first $100,000 plus $6 per additional $1,000; $500,001+: $2,796 plus $3 per $1,000 above $500,000
- Payment note
- Stuart separately publishes city impact fees for qualifying new development. Examples include single-family detached total city impact fees of $2,143.43 per unit and commercial total city impact fees of $2,190.81 per 1,000 square feet of floor area.
Fees change. Verify current amounts at the official fee schedule.
Work That Does NOT Require a Permit
- Nonresidential farm buildings on farms
- Certain temporary construction sheds
- Surfacing of floors or slabs with carpet, tile, brick, wood, or other finish materials
- Residential playground equipment without electrical service
Important: These are Florida Building Code exemptions only. Other state and county departments or agencies may still require approvals or permits.
Inspections
How to Schedule
- 772-600-1212 (phone)
Additional Resources
- Building code: 2023 Florida Building Code, 8th Edition, effective December 31, 2023
- Development Fee Schedule
- Permit Exemptions
- License lookup guide: Florida Contractor License Requirements
- Contract template: Florida Homeowner-Contractor Agreement
- Florida hub: Florida Contractor License & Permit Hub
Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the City of Stuart Building Division before applying.
Need help with your project?
Navigating permits in Stuart can be complicated.
Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.
Learn how Jaspector worksOther cities in Martin County
View all Martin County jurisdictions →