Town of Jupiter Island, FL Building Permit Guide

How to apply for a building permit in Town of Jupiter Island, Florida. Permit authority, application steps, fees, and inspection requirements.

Florida Martin County Updated March 2026

Permit Authority

The town operates its own building department for properties within town limits, including the Martin County portion of Jupiter Island.

Department
Town of Jupiter Island Building Department
Address
2 Bridge Road, Hobe Sound, FL 33455
Phone
772-545-0150

Online Permit Portal

Platform: Direct submission with paper and digital copies • Account required: No • Submission: In-person only

Application Process

  1. Confirm the property is within Jupiter Island town limits.
  2. Review the town's permit forms and identify whether Development Review Board approval is required before permit processing.
  3. Prepare the permit application, project description, plans, and supporting documents.
  4. Submit one paper set of plans and, for larger projects, a digital copy as directed on the town's permit application.
  5. Pay the permit fee and Florida surcharges calculated from the stated construction value.
  6. Complete required inspections through the Building Department.
  7. Before final closeout, satisfy any Certificate of Occupancy or Certificate of Completion checklist items, including final cost certification and any utility or right-of-way signoffs if applicable.

Source: Town of Jupiter Island Building Department

General Requirements

Any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or perform regulated trade work must first apply to the building official and obtain the required permit.

Required Documents

  • Permit application
  • Scope of work
  • Plans
  • Subcontractor information
  • Owner-builder affidavit where applicable
  • Notice of commencement
  • Revision forms
  • Trade affidavits
  • Project-specific certifications
Permit validity
Permit is valid for 18 months from issuance, becomes null and void if work is not commenced within 6 months or is suspended or abandoned for 6 months, and is considered suspended or abandoned if it does not pass an inspection within 180 days.
Building code
2023 Florida Building Code, 8th Edition, effective December 31, 2023

Fees

Minimum permit fee
$25
Permit fee formula
1.5% of total job or construction value (minimum $25) plus Florida surcharges of 2.5% of the permit fee
Payment note
Final construction cost certification can trigger additional permit fees using the same 1.5% town permit fee plus 2.5% surcharges formula.

Fees change. Verify current amounts at the official fee schedule (effective 2025).

Work That Does NOT Require a Permit

Contact the Town of Jupiter Island Building Department to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • 772-545-0150 (phone)
  • building@tji.martin.fl.us (email)

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Town of Jupiter Island Building Department before applying.

Need help with your project?

Navigating permits in Town of Jupiter Island can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.

Other cities in Martin County

View all Martin County jurisdictions →