Greenlee County Building Permit Guide (Unincorporated Area)

How to apply for a building permit in unincorporated Greenlee County, Arizona. Permit authority, application steps, fees, and inspection requirements.

Arizona Updated March 2026

Permit Authority

All properties in unincorporated areas of Greenlee County, excluding incorporated Towns of Clifton and Duncan.

Department
Greenlee County Planning and Zoning Department
Address
253 Fifth St., Clifton, AZ 85533 (Engineer's Office, second floor of annex next to Health Department)
Phone
(928) 865-4762

Online Permit Portal

Platform: SmartGov • Account required: Yes • Submission: Online only

Application Process

  1. Determine whether your project requires a zoning use permit, building permit for site-built home, and/or floodplain permit.
  2. Complete the zoning permit application and submit through SmartGov portal or in person at Planning and Zoning.
  3. Some permits may be issued by telephone; contact Planning and Zoning to discuss your project.
  4. Pay the zoning use permit fee (no charge for building permit when issued with zoning permit).
  5. For manufactured homes or septic systems, contact Greenlee County Health Department for separate permits.
  6. Obtain confirmation of permit approval and zoning authorization before beginning work.

Typical processing time: Varies; contact county for specific project timelines.

Source: Greenlee County Planning and Zoning Department

General Requirements

Building permits are required for construction of site-built homes and development on private property in unincorporated Greenlee County. Zoning use permits are required in most cases. Floodplain permits are required for work in flood-prone areas.

Required Documents

  • Completed permit application
  • Zoning permit application
  • Plans or drawings (if required for specific project)
  • Special power of attorney form (if applicable)
Building code
None. Greenlee County has not adopted a building code. The county processes permits for zoning and floodplain compliance, but does not conduct plan review, construction inspection, or issue certificates of occupancy.

Fees

Permit fee formula
Building permit is issued at no cost when zoning use permit is issued; fee is charged for zoning use permit. Consult county for current fee schedule.

Work That Does NOT Require a Permit

Contact the Greenlee County Planning and Zoning Department to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • (928) 865-4762 (phone)

Typical inspection sequence: Greenlee County does not conduct construction inspections or issue certificates of occupancy. Zoning and floodplain compliance is verified administratively.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Greenlee County Planning and Zoning Department before applying.

Need help with your project?

Navigating permits in Unincorporated Greenlee County can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.