Town of Eagar, AZ Building Permit Guide

How to apply for a building permit in Town of Eagar, Arizona. Permit authority, application steps, fees, and inspection requirements.

Arizona Apache County Updated March 2026

Permit Authority

All properties within the incorporated Town of Eagar.

Department
Town of Eagar Community Development / Building
Address
22 W. 2nd St., PO Box 1300, Eagar, AZ 85925
Phone
(928) 333-4128 ext. 222

Online Permit Portal

Platform: In-person and paper submittal • Account required: No • Submission: In-person only

Additional resources:

Application Process

  1. Obtain and complete the appropriate permit application (Residential Building Permit, Commercial Building Permit, Demolition Permit, Electrical Permit, Plumbing Permit, or Manufactured Home Permit).
  2. Prepare construction plans and specifications according to town building and zoning codes.
  3. Prepare a site plan or property information.
  4. Submit the application and all required documents to the Community Development office.
  5. Town staff reviews the application for completeness and code compliance.
  6. Approvals are normally given within six working days.
  7. Pay permit fees upon approval.
  8. Obtain the building permit and schedule required inspections.
  9. Request inspections at least 24 hours in advance.
  10. Complete all required inspections before occupying the structure.

Typical processing time: Approvals are normally given within six working days.

Source: Town of Eagar Community Development / Building

General Requirements

Compliance with Eagar building and zoning codes is mandatory for all construction and development in Eagar.

Required Documents

  • Completed residential or commercial building permit application
  • Construction plans and specifications
  • Site plan or property sketch
  • Applicant and property-owner identification and contact information
  • Project cost estimate or valuation
Permit validity
Permits expire after 360 days unless extended.
Building code
2018 International Residential Code (IRC), 2018 International Building Code (IBC), 2018 International Plumbing Code (IPC), 2018 International Mechanical Code (IMC), 2018 International Property Maintenance Code (IPMC), 2018 International Fire Code (IFC), and 2011 National Electrical Code (NEC)

Work That Does NOT Require a Permit

Contact the Town of Eagar Community Development / Building to confirm whether your project requires a permit before starting work.

Inspections

How to Schedule

  • (928) 333-4128 ext. 222 (phone)
Scheduling deadline
Inspection requests must be submitted at least 24 hours in advance.

Typical inspection sequence: Inspections are required for all phases of construction.

Additional Resources

Information on this page was last verified: March 2026. Permit rules and fees change — confirm current requirements directly with the Town of Eagar Community Development / Building before applying.

Need help with your project?

Navigating permits in Town of Eagar can be complicated.

Jaspector connects you with local experts who can review your scope, verify your contractor, and help you understand what permits your project actually needs.

Learn how Jaspector works
Important: This page is an educational resource provided by jaspector.com. It is not legal advice, and it does not substitute for official guidance from the permit authority listed above. Permit requirements, fees, and processes change frequently. Always verify current requirements directly with the issuing department before beginning any construction project. Use of this page does not create an attorney-client relationship. Jaspector assumes no liability for any outcomes arising from reliance on this information.